Machine Studies

Draft Schedule for Run01-7, 2022

March 14th 0800 – March 16th 0800



Time

Descriptions

Studiers

SR Status


Monday, March 14, 2022



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Hahne

Stored Beam & Injection

0930-1130

Install metasys pvs

Smith

Stored Beam & Injection

0930-1230

Swap broken S36 amp w/ S2 amp

Zabel

No Beam

1000-1130

APS-U piping mock up

MOM

Access Zone A

1130-1200

SR recovery. 324 bunches.

Ops

Stored Beam & Injection

1200-1400

Apply proposed reduced ID35 steering. Hybrid mode setup.

Emery Yipeng

Stored Beam & Injection

1400-1900

Hybrid mode Orbit setup

Yipeng

Stored Beam & Injection

1900-2200

6 GeV low alpha check-out

Emery Kallakuri Brill

Stored Beam & Injection

2200-2400

Open




Tuesday, March 15, 2022



0000-0500

Open



0500-0700

Injector training

Hotham/Ronzhin

Limited Injection

0700-0900

Investigate RTFB interlock action from RF klystron status

Xu

Stored Beam & Injection

0900-1300

swap cables for S2 and S35 Dimtel of FT/R9 in A014, and repeat disconnection tests

Brill Emery

Stored Beam & Injection

1300-1700

linac RG1/RG2 optimizer debugging

Kuklev Shang

Stored beam & No Injection

1300-1700

SR coupling optimization

Yipeng

Stored beam & No Injection

1700-2100

6 GeV low alpha RTFB loops

Kallakuri Brill Emery

Stored Beam & Injection

21000-2400

Further hybrid mode checkout.


Stored Beam & Injection


Wednesday, March 16, 2022



0000-0500

Open


Stored Beam & Injection

0500-0700

Injector training

Hotham/Ronzhin

Limited Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection