Machine Studies

Draft Schedule for Run02-12, 2022

September 19th 0800 – September 20th 0800



Time

Descriptions

Studiers

SR Status


Monday, September 19, 2022



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Hahne

Stored Beam & Injection

0930-1130

DG645 work reboot timing IOCs

Hong

No Beam

0930-1130

Investigate/repair K2 arc detector monitor

Fystro DiMonte

No Injection

0930-1130

Check Booster Dipole Current Interlock w/BEK discharge signal 

Rafael / Puttkammer

No Injection

0930-1030

Troubleshoot S4A:H4

Vargas

No Beam

1030-1130

Investigate S33B:H4 Mag OT

Vargas

No Beam

1130-1200

Recover SR

Ops

Stored Beam & Injection

1200-1400

Linac training

Weber/Ronzhin

Limited Injection

1400-1600

PEM for Linac RF down-mode switching

Soliday Fystro

Stored Beam & No Injection

1600-2000

Unified Feedback test 324 bunches

Kallakuri Sereno Brill

Stored Beam & No Injection

1600-1800

Test the prototype BTS BESOCM with beam through BTS. 1Hz. Compatible with stored beam above

Keane

Stored Beam & No Injection

2000-2300

Beam steering

Yipeng

Stored Beam & Injection

2000-2200

Test 1 Hz/2Hz B:EK for SCR energy check & septa FF switch. Compatible with stored beam above

Shang, Emery, Harkay

Stored Beam & Injection

2300-2400

Bunch purity checkout 1 Hz

Yipeng

Stored Beam & Injection


Tuesday, September 20, 2022



0000-0200

Linac training for Ihar

Lobach Yin-e

Stored Beam & No Injection

0200-0400

SR Injection checkout

Emery

Stored Beam & Injection

0400-0600

Top verification at 1 Hz with compensatory value for time interval

Ops

Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection