Machine Studies

Draft Schedule for Run02-5, 2022

June 27th 0800 – June 29th 0800



Time

Descriptions

Studiers

SR Status


Monday, June 27, 2022



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Hahne

Stored Beam & Injection

0930-1530

Connect K2 waveguide

RF Group

No Injection

1000-1200

25ID beamline work

Boron

No Beam

1000-1100

S37 cav2 investigation

RF Group

Access Zone F

1000-1200

Test pem for changing defaultXRDP and defaultXRDP.fullSVs together

Shang

No Beam

1000-1300

DG465 implementation. Try to inject into SR at 1300h.

Hong

No Beam

1000-1300

BTS grounding measurements

Diag

Access Booster

1100-1300

APS-U reference point measurement RF on

RF Group

No Beam

1300-1400

SR recovery

OPS

Stored Beam & Injection

1400-1900

Orbit Switch with an update on procedure

Yipeng Shang Emery

Stored Beam & Injection

1900-2300

X-ray bpm mombo scans (can start earlier if orbit switch finished early)

Sereno Shang

Stored Beam & Injection

2300-0200

6 GeV setup training

Yipeng

Stored Beam & Injection


Tuesday, June 28, 2022



0200-0500

Calibrate Dimtel inputs and outputs for present configuration

Emery

Stored Beam & Injection

0500-0800

Diagnostics of timing signals

Hong

Stored Beam & Injection

0800-1000

Install line-conditioning transformer at RF-1

Madden

No beam

0800-1000

K2 validations

RF Group/OPS

No Injection

1000-1400

Test automatic LB+ timing script

Brill Sereno

Stored Beam & Injection

1400-1800

Booster chromaticity. Need to change rf frequency.

Yao

No Stored Beam

1800-2100

Tune feedforward with ID gaps

Emery

Stored Beam & Injection

2100-2400

IEX/CPU measurement and correction training

Yipeng Emery

Stored Beam & Injection


Wednesday, June 29, 2022



0000-0300

Open


Stored Beam & Injection

0300-0630

Open


Stored Beam & Injection

0630-0800

Prepare for User beam

OPS

Stored Beam & Injection