Draft Schedule for Run02-7, 2022

July 11th 0800 – July 12th 0800



Time

Descriptions

Studiers

SR Status


Monday, July 18, 2022



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Hahne

Stored Beam & Injection





0930-1030

RF waveguide switch

RF Group

No Beam

0930-1030

Reboot datapool ioc and check S25C:V1 sign problem

Xu

No Beam





1000-1100

Modify Booster ICT ground strap

Keane

Access Booster

1100-1200

SR recovery (hybrid pattern)

Ops

Stored Beam & Injection

1200-1400

Booster training

Orne/Hotham

Limited Injection

1200-1400

Check S25 CU steering

Shang

Limited Injection

1400-1800

Unified feedback test

Kallakuri Brill Sereno

Stored Beam & Injection

1800-2000

LB+ timing test

Brill Sereno

Stored Beam & Injection

2000-2200

Linac training (15-23)

Weyer/Hughes

No Impact

2200-0100

Hybrid mode setup training

Yipeng

Stored Beam & Injection


Tuesday, July 19, 2022



0100-0500

Linac ML

Kuklev

No injection

0500-0700

Hybrid mode checkout (because there is always “something”)

Emery

Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection