Draft Schedule for Run02-7, 2022
July 11th 0800 – July 12th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, July 18, 2022 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Hahne |
Stored Beam & Injection |
|
|
|
|
0930-1030 |
RF waveguide switch |
RF Group |
No Beam |
0930-1030 |
Reboot datapool ioc and check S25C:V1 sign problem |
Xu |
No Beam |
|
|
|
|
1000-1100 |
Modify Booster ICT ground strap |
Keane |
Access Booster |
1100-1200 |
SR recovery (hybrid pattern) |
Ops |
Stored Beam & Injection |
1200-1400 |
Booster training |
Orne/Hotham |
Limited Injection |
1200-1400 |
Check S25 CU steering |
Shang |
Limited Injection |
1400-1800 |
Unified feedback test |
Kallakuri Brill Sereno |
Stored Beam & Injection |
1800-2000 |
LB+ timing test |
Brill Sereno |
Stored Beam & Injection |
2000-2200 |
Linac training (15-23) |
Weyer/Hughes |
No Impact |
2200-0100 |
Hybrid mode setup training |
Yipeng |
Stored Beam & Injection |
|
Tuesday, July 19, 2022 |
|
|
0100-0500 |
Linac ML |
Kuklev |
No injection |
0500-0700 |
Hybrid mode checkout (because there is always “something”) |
Emery |
Stored Beam & Injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |