Draft Schedule for Run03-11, 2022
December 20nd 0000 – December 20nd 2400
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, December 20, 2022 |
|
|
0000-0010 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0010-0300 |
Run 1 Hz topup, measure bunch purity |
OPS |
Stored Beam & Injection |
0300-0700 |
Open |
|
Stored Beam & Injection |
0700-0900 |
SR console test |
Hotham |
Stored Beam & Injection |
0900-1100 |
High charge in injectors (10 nC) |
Calvey, Harkay |
Stored Beam & Injection |
1100-1200 |
HP surveys, beam to BTX, 4, 8, 10 nC. (rope off BTS area) |
HP group |
Stored Beam & Injection |
1100-1200 |
BTS ICT data |
Sereno, Brill, Keane |
Stored Beam & Injection |
1200-1500 |
10 nC charge stability studies in booster |
Calvey, Madden |
Stored Beam & Injection |
1500-1900 |
Unified feedback |
Kallakuri, Brill, Sereno
|
Stored Beam & Injection |
1600-1900 |
Troubleshoot ITS (in parallel with stored beam above) |
Waldschmidt |
Stored Beam & No Injection |
1900-2100 |
Troubleshoot SCR restore of PAR timing |
Yao, Shang |
Stored Beam & Injection |
2100-2200 |
Open |
|
Stored Beam & Injection |
2200-2400 |
Slow Shutdown |
OPS |
No Beam |