Machine Studies
Draft Schedule for Run03-2, 2022
October 10th 0800 – October 11, 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, October 10, 2022 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Hahne/Sereno |
Stored Beam & Injection |
0930-1030 |
Reboot siocrunctrl2 |
Xu |
Stored Beam & Injection |
0930-1130 |
Linac PEM testing |
Fystro/Soliday |
Limited Injection |
0930-1130 |
K2 work |
Meyer/Wang |
No Injection or K2 down mode |
0930-1130 |
RF-2 readback correction |
Trento |
No Beam |
0930-1130 |
Investigate S31 communication problem |
Puttkammer |
No Beam |
0930-1130 |
Fix faulty digital readback for S4A:H4 |
Vargas |
No Beam |
0930-1130 |
Investigate P1H1 power supply |
Vanis |
Limited Injection |
1130-1300 |
Booster console |
Hotham/Fystro |
Limited Injection |
1300-1500 |
Linac training (7-15) |
Weyer/Schiltz |
Limited Injection |
1500-1700 |
Investigation of topup computations (1Hz/2Hz injections) |
Shoaf Pietryla |
Stored Beam & Injection |
1700-2000 |
IEX checkout |
Yipeng |
Stored Beam & Injection |
2000-2200 |
6 GeV check of optics correction of 11-m betay in sector 35 |
Emery |
Stored Beam & Injection |
2200-2400 |
6 GeV measure mom. aperture of “symmetric” lattice |
Emery |
Stored Beam & Injection |
|
Tuesday, October 11, 2022 |
|
|
0000-0200 |
Run through of Dimtel calibration process (7 GeV) |
Emery |
Stored Beam & Injection |
0200-0400 |
Check of loop stability with WS-based orbit correction with A:H3/B:H4 (7 GeV) |
Emery |
Stored Beam & Injection |
0400-0500 |
Open |
|
|
0500-0700 |
Linac training (23-07) |
Weber/Ronzhin |
Limited Injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |