Machine Studies

Draft Schedule for Run03-3, 2022

October 17th 0800 – October 18th, 0800



Time

Descriptions

Studiers

SR Status


Monday, October 17, 2022



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Hahne/Sereno

Stored Beam & Injection

0930-1230

RF-1 cav 40 phase measurements

RF Group

No Beam

0930-1130

Investigate S31 communication error

Puttkammer/ CTLs

No Beam

0930-1130

Fix faulty S4A:H4 readback

Vargas

No Beam

0930-1130

Install Sola transformer in IK1

Harris

No Beam

0930-1130

changes to the LPL_configure PEM with linac K1 and K3 up and down

Soliday

No Beam

1130-1200

Reboot siocrunctrl2

Xu

No Beam

1200-1300

Re-install Ion Pump process meter

Trento

No Injection

1300-1500

IH/HP studies

Henry

Controlled Access Zone F

1300-1500

RF phase error measurements

Trento

No Beam

1400-1500

Gas study setup

Hoyt/Calvey

Controlled Access Zone E

0930-1130

Linac training

Weber/Ronzhin

Limited Injection

1130-1330

Linac training

Schiltz/Weyer

Limited Injection

1500-1515

Open. To allowed closures.



1500-1800

Intermittent linac training subject to beam requirement of parallel study

Banks/LaBuda

No Impact

1530-1800

6 GeV setup (new lattice checkout)

Emery

Stored Beam & Injection

1530-1800

Pinhole camera checkout

Yang

Stored Beam & Injection

1800-2400

Gas injection experiment at 6 GeV

Calvey, Hoyt, Kallakuri, Emery

Stored Beam & Injection


Tuesday, October 18, 2022



0000-0030

7 GeV setup

Emery/Yipeng

Stored Beam & Injection

0030-0230

ID feedforward measurement (7 GeV)

Yipeng

Stored Beam & Injection

0230-0700

Open


Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection