Machine Studies
Draft Schedule for Run03-9, 2022
December 5th 0800 – December 7th, 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, December 5, 2022 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Sereno |
Stored Beam & Injection |
0900-1030 |
Linac console |
Fystro/Weber |
Limited Injection |
0930-1130 |
Process H2O diagnostics |
Wright |
No Beam SR PS at 0 |
1000-1200 |
25ID Gap troubleshooting |
Xu, Gagliano |
Access Zone D |
1030-1230 |
Replace pinger magnet fan blower |
Wright |
Access Zone F |
1030-1230 |
Test B:BM safety ramp |
Wang, Yao |
No Injection |
1030-1230 |
Troubleshoot PAR BM supply |
Puttkammer |
No Injection |
1030-1230 |
Check Linac GESPAC configuration |
Ruan |
Limited Injection |
1030-1430 |
Install RF gun in ITS |
Waldschmidt |
No Injection |
1030-1430 |
Install new K2 shutdown circuit |
Meyer |
No Injection |
1430-1500 |
Recover SR |
Ops |
Stored Beam & Injection |
1500-1600 |
P1 Bpm offset adjustments for 24 bunches |
Emery |
Stored Beam & Injection |
1600-2100 |
Orbit switch from hybrid to 24 bunches |
Yipeng |
Stored Beam & Injection |
2100-2300 |
Linac training |
Weyer/Schiltz |
Stored Beam & Injection |
2300-2400 |
Optimize PAR injection eff in 1 Hz |
Harkay |
Stored Beam & Injection |
|
Tuesday, December 6, 2022 |
|
|
0000-0100 |
Check operator 1Hz/2Hz switch pem without restoring PAR Timing |
Harkay |
Stored Beam & Injection |
0100-0500 |
Open |
|
|
0500-0700 |
SR training (23-07) |
Berkland/Hotham |
Stored Beam & Injection |
0700-0730 |
Open |
|
Stored Beam & Injection |
0730-1130 |
Install RF gun in ITS |
Waldschmidt |
No Injection |
0730-1130 |
APS-U survey network ties |
Jansma |
Authorized Access Zone C |
1130-1200 |
Recover SR |
Ops |
Stored Beam & Injection |
1200-1800 |
1 Hz/2 Hz topup checkout (details below) |
Harkay et al |
Stored Beam & Injection |
|
|
|
|
|
|
|
|
1200-1600 |
1Hz/2Hz efficiency calculation studies |
Shoaf, Pietryla, Emery, Harkay |
Stored Beam & Injection |
1600-1800 |
Run topup with new mtime sequence program in 1Hz and 2Hz |
Ops, Harkay |
Stored Beam & Injection |
1800-2400 |
Unified Feedback test. 324 bunches |
Kallakuri, Sereno, Brill |
Stored Beam & Injection |
2100-2300 |
Linac training (compatible with 324 bunch in SR above) |
Weyer/Schiltz |
Limited Injection |
2300-2400 |
TBD |
Emery |
Stored Beam & Injection |
|
Wednesday, December 7, 2022 |
|
|
0000-0430 |
TBD |
Emery |
Stored Beam & Injection |
0430-0630 |
SR training (23-07) |
Berkland/Hotham |
Stored Beam & Injection |
0630-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |