Machine Studies

Draft Schedule for Run01-10, 2023

April 3rd 0800 – April 4th 0800



Time

Descriptions

Studiers

SR Status


Monday, April 3, 2023



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0900-1100

Replace S34 cabinet 4 GESPAC

Puttkammer

No Beam

0900-1100

Johnson controls work

Wright

No Beam S23-30 PS at zero

0900-1300

Convert abort kicker to fan out kicker

Dooling/MOM/Vanis

Access Zone F

0900-1300

Repair water leak at K5

Meyer

Access Zone F

0900-1100

Test pem for high-charge PAR

Harkay, Shang

Access Zone F

0900-1000

Linac BPM configuration

Hong

Access Zone F

1100

Restore previous SR orbit correction configuration

Fystro

Access Zone F

1300-1500

Linac training (after repair of K5 water leak)

Schiltz/Berkland

Limited Injection

1500

Fill 102 mA 324 bunches. See parallel SR studies till 2100 below

Ops

Stored Beam & Injection

1500-1700

29-ID measurements of vertical emittance. Shutters open.

Wootton

Stored Beam & Limited Injection

1500-1600

Injection Charge Control

Yine, Arnold

Stored Beam & Injection

1600

Refill SR if needed

Ops

Stored Beam & Injection

1600-2100

RG1 beam tune-up

Lobach

Stored Beam & Limited Injection

1700-1900

SCU1 FF table with external correctors

Emery

Stored Beam & Limited Injection

1800-2000

Test getxytunesDimtel script for driving single bunches for tune measurement

Kallakuri, Shang

Stored Beam & Limited Injection

2000-2100

Fan-out kicker calibration

Dooling

Stored Beam & Limited Injection

2100-2400

6 GeV. Optics correction RHB-S7S37. Top-up.

Emery

Stored Beam & Injection


Tuesday, April 4 2023



0000-0300

6 GeV. Optics correction RHB-S7S37

Emery

Stored Beam & Injection

0300

7 GeV fill 100 mA 24 bunches. Scraper conditioning

Dooling

Stored Beam & Limited Injection

0300-0500

Adaptive BO in linac

Kuklev

Stored Beam & Limited Injection

0500-0700

Booster training

Weyer/Weber

Limited Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection