Machine Studies

Draft Schedule for Run01-11, 2023

April 10th 0800 – April 11th 0800



Time

Descriptions

Studiers

SR Status


Monday, April 10, 2023



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0800-1300

ITS waveguide work

RF group

No Injection

0900-1100

Put more capacitors in SR vertical kicker

PS group

Access Zone A

0900-1000

APS-U contractor tours

Erdman

Access Zone A

1030-1300

Individual shutter control, Beam permit, BTS and SR at 7 GeV, but no actual beam

Smith

No Beam, No Injection

1300

Set up BTS and SR with 6 GeV RHB-S7S37

Emery

Stored Beam & Injection

1300-1500

Booster training (7-15)

Weyer/Weber

Limited Injection

1300-1500

Linac training (7-15)

Schiltz/Weyer

Limited Injection

1500-1700

6 GeV RHB-S7S37, 100 mA 24 bunch top-up for HP surveys in corridor

Ops, HP

Stored Beam & Injection

1700-2000

360 Hz filter test on RF4. 6 GeV RHB-S7S37

Berenc, Emery, Horan

Stored Beam & Injection

2000-2400

6 GeV RHB-S7S37 orbit bumps, scraper conditioning, scraper P1 offset, kicker calibration – and more

Emery, Dooling

Stored Beam & Injection

2100-2300

Linac training (15-23) while SR beam is stored

LaBuda/Novencido

Limited Injection


Tuesday, April 11, 2023



0200-0430

6 GeV RHB-S7S37 orbit bumps, scraper conditioning, scraper P1 offset, kicker calibration – and more

Emery Dooling

Stored Beam & Injection

0400-0500

ITS access for water and vacuum group

MOM

Stored Beam and No Injection

0430-0500

7 GeV SR recovery

Emery

Stored Beam & Injection

0500-0700

MOBO on SR

Kuklev, Shang, Emery

Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection