Machine Studies
Draft Schedule for Run01-2, 2023
February 6th 0800 – February 7th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, February 6, 2023 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Sereno |
Stored Beam & Injection |
0930-0945 |
Switch to 1 Hz, verify with PAR beam |
Ops |
No beam |
1000-1130 |
Pinhole camera repair |
Wright |
Access Zone E |
1030-1330 |
Authorized access to linac/PAR (to cover the multiple work requests below) |
Ops |
Access Zone
E |
0930-1130 |
S18:19 communication error |
Yang Ruan |
No Beam |
0930-1130 |
Troubleshoot S4B:Q1 |
Vargas |
No Beam |
1000-1400 |
Booster BM tests (1 Hz) |
Calvey/Shang |
Access Zone E |
0930-1230 |
Troubleshoot SR RF-3 |
Trento |
No Beam |
1000-1330 |
Inspect rf gun and alpha magnet beam lines at rg1 and rg2 |
Waldschmidt |
Access Zone
E |
1000-1130 |
Repair ITS YAG1 |
Berg |
Access Zone
E |
1000-1130 |
Swap digital LLRF at K2. Check with beam later. |
Yawei |
Access Zone
E |
1130-1330 |
Troubleshoot linac FS3 |
Dombrowski |
Access Zone
E |
1130-1330 |
Align PAR bypass cube4 and inspect PAR FL4 |
Berg |
Access Zone
E |
1345-1500 |
SCU1 measurement, shutter closed |
Emery |
Stored Beam & Injection |
1500-1800 |
SCU1 beam with shutters open |
Emery |
Stored Beam & Injection |
1800-2200 |
RG1 (start with 1 Hz and end with 1 Hz) |
Yine, Fystro, Ihar |
Beam and No Injection |
2200-0100 |
PAR efficiency |
Ihar, Yao |
Beam and No Injection |
|
Tuesday, February 7, 2023 |
|
|
0100-0300 |
Topup 1 Hz verification |
Ops |
Stored Beam & Injection |
0300-0500 |
Linac training |
Novencido/ LaBuda |
Limited Injection |
0500-0700 |
Bunch Purity (1 Hz) |
Yipeng, Harkay |
Stored Beam & Injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |