Machine Studies

Draft Schedule for Run01-3, 2023

February 13th 0800 – February 14th 0800



Time

Descriptions

Studiers

SR Status


Monday, February 13, 2023



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Sereno

Stored Beam & Injection

1000-1100

Investigate 33ID water leak

Wright

Access Zone E

1000-1100

Check K2 connections

Meyer

No Injection

1100-1130

Connect SCU1 temperature monitoring

Martens

Access Zone A

1000-1200

Fix Linac/PAR diag flags

Dombrowski

Access Linac

1200-1300

Recover SR. fill 324 bunches

Ops

Stored Beam & Injection

1300-1500

Linac training

Novencido/ Orne/Berg

Limited Injection

1500-1900

RG1 study. HP needed

Yine, Fystro, Lobach

No injection

1500-2100

SCU1 corrector adjustment. 324 bunches. Shutters open.

Emery, Kesgin, Shastri

Stored Beam & No Injection

1900-2100

Refill of SR if necessary

Ops

Stored Beam & Injection

2100-2300

PAR training

Weyer/Schiltz

Limited Injection

2300-2400

Dimtel model calibration

Emery

Stored Beam & Injection


Tuesday, February 14, 2023



0000-0200

PAR efficiency. Inject into SR as needed.

Yao, Shang

Stored Beam & Injection

0200-0400

Nonlinear optics knobs

Yipeng

Stored Beam & Injection

0400-0700

Open


Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection