Machine Studies

Draft Schedule for Run01-5, 2023

February 27th 0800 – February 28th 0800



Time

Descriptions

Studiers

SR Status


Monday, February 27, 2023



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0830-1000

IR sensor replacement

Wright

Possible Zone F Access

0830-1030

K2 with digital LLRF. Run with this for whole intervention period. Recover in morning.

Yawei, others for training

No injection

1030-1100

SR recovery. Fill 324 bunches 100mA

Ops

Stored Beam & Injection

1100-1200

Setup various x-y couplings, and finally fill one bunch 0.4 mA

Emery

Stored Beam & Injection

1200-1400

Injector training (07-15)

Weyer/Schiltz

Limited Injection

1200-1400

Dimtel tune measurement with coupling. Single bunch.

Kallakuri, Emery

Limited Injection

1400-1500

SR script tests (provisional)

Kuklev, Emery

Stored Beam & Injection

1500-1800

Check out a 6 GeV lattice, RHB-S7 (ions) or RHB-S7S37 (scraper). Plus drive-damp check-out

Emery, Kallakuri

Stored Beam & Injection

1800-2300

SCU compensation. 324 bunches. Can be extended though the RG1 study

Emery, Shastri, Kesgin

Stored Beam & Interleaving Injection

1800-2000

Transport RG2 electron beam to Booster Bypass beam dump

Wootton

Stored Beam & Interleaving Injection

2000

Refill if needed (for SCU1)

Ops

Stored Beam & Injection

2230-0430

RG1 optimization (could start earlier)

Ihar, Kuklev

No injection


Tuesday, February 28, 2023



2230-0430

RG1 optimization

Ihar, Kuklev

No injection

0430-0630

PAR training (23-07)

Weber/Ronzhin

Limited Injection

0630-0700

Recover K2 Digital LLRF

RF group

No injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection