Machine Studies
Draft Schedule for Run01-5, 2023
February 27th 0800 – February 28th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, February 27, 2023 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0830-1000 |
IR sensor replacement |
Wright |
Possible Zone F Access |
0830-1030 |
K2 with digital LLRF. Run with this for whole intervention period. Recover in morning. |
Yawei, others for training |
No injection |
1030-1100 |
SR recovery. Fill 324 bunches 100mA |
Ops |
Stored Beam & Injection |
1100-1200 |
Setup various x-y couplings, and finally fill one bunch 0.4 mA |
Emery |
Stored Beam & Injection |
1200-1400 |
Injector training (07-15) |
Weyer/Schiltz |
Limited Injection |
1200-1400 |
Dimtel tune measurement with coupling. Single bunch. |
Kallakuri, Emery |
Limited Injection |
1400-1500 |
SR script tests (provisional) |
Kuklev, Emery |
Stored Beam & Injection |
1500-1800 |
Check out a 6 GeV lattice, RHB-S7 (ions) or RHB-S7S37 (scraper). Plus drive-damp check-out |
Emery, Kallakuri |
Stored Beam & Injection |
1800-2300 |
SCU compensation. 324 bunches. Can be extended though the RG1 study |
Emery, Shastri, Kesgin |
Stored Beam & Interleaving Injection |
1800-2000 |
Transport RG2 electron beam to Booster Bypass beam dump |
Wootton |
Stored Beam & Interleaving Injection |
2000 |
Refill if needed (for SCU1) |
Ops |
Stored Beam & Injection |
2230-0430 |
RG1 optimization (could start earlier) |
Ihar, Kuklev |
No injection |
|
Tuesday, February 28, 2023 |
|
|
2230-0430 |
RG1 optimization |
Ihar, Kuklev |
No injection |
0430-0630 |
PAR training (23-07) |
Weber/Ronzhin |
Limited Injection |
0630-0700 |
Recover K2 Digital LLRF |
RF group |
No injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |