Draft Schedule for Run01-6, 2023

March 6th 0800 – March 8th 0800



Time

Descriptions

Studiers

SR Status


Monday, March 6, 2023



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Sereno

Stored Beam & Injection

0930-0940

Reboot interleaving DSPs

Puttkammer

No Injection

1000-1200

Swap out 19B:Q2

PS Group

No Beam

1000-1200

RF cavity phase adjustments

Goel

No Beam SRRF systems up

1000-1200

Fix flag L3:AM:FS1

Dombrowski

Access Linac

1000-1200

APS-U measurements

Campbell

Access Booster

1000-1400

K2 ACIS interface modification

Meyer

No Injection/K2 down after 12:00

1030-1130

Unlock air to BTL stop

Wooton

Access Booster

1030-1130

Install stop blocks on Actuators for screens

Erwin

Access Booster

1200-1400

PAR console

Fystro/Weber

Limited Injection

1200-1400

Tag components for harvesting

Clute/Knopp

Access Zone B & C

1400-1500

Injector training (one hour only)

Weyer/Schiltz

Limited Injection

1400-1500

K2 linac training (parallel with above)

Fystro

Limited Injection

1500-1700

Linac training

LaBuda/ Novencido

Limited Injection

1500-1700

No beam SR software checkout for MGGPO

Kuklev

Limited Injection

1700-1900

SR recovery and Hybrid mode checkout

Emery

Stored Beam & Injection

1900-2300

Hybrid mode orbit recovery

Yipeng

Stored Beam & Injection

2300-0100

MGGPO script and injection checkout

Emery, Shang, Kuklev

Stored Beam & Injection


Tuesday, March 7, 2023



0100-0300

Checkout 6 GeV RHB-S7S37

Emery

Stored Beam & Injection

0300-0500

Apply LUT and FF corrector tables to SCU1. 324 bunches.

Emery

Stored Beam & Injection

0500-0700

Hybrid topup checkout, ID gaps closed, shutters open for ID1

Ops

Stored Beam & Injection. Shutter permit.

0700

Dump and fill 324 bunches. (close shutter, open gaps, fill, then re-open shutters)

Ops

Stored Beam & Injection

0700-1300

SCU1 photon beam checkout by ID1

Shastri

Stored Beam & No Injection. Shutter permit.

0700-0900

Injector training (07-15)

Weyer/Schiltz

Limited Injection

0900-1300

RG2 beam to LEA

Wootton and many others

No Injection

1300-1500

Injector training (07-15)

Weber/Ronzhin

Limited Injection

1500

Dump and fill 24 bunches

Ops


1500-1700

P1 offset measurement (some sectors)

Sajaev

Stored Beam & No Injection

1500-1700

Linac training (15-23)

LaBuda/ Novencido

Limited Injection

1700

Fill ring 100 mA 24 bunches and let decay

Ops

Stored Beam & Injection

1700-2000

S37 scraper conditioning

AOP

Stored Beam & No injection

1700-2300

RG1 injection optimization

Lobach, Kuklev, Dooling

Stored Beam & No injection

2300-2400

Nonlinear knob

Yipeng

Stored Beam & Injection


Wednesday, March 8, 2023



0000-0200

Nonlinear knob

Yipeng

Stored Beam & Injection

0200-0600

MPGGO RHB-S4S7S32 7 GeV

Emery, Kuklev, Shang

Stored Beam & Injection

0600-0630

Recover for hybrid mode

Emery

Stored Beam & Injection

0630-0800

Prepare for User beam

OPS

Stored Beam & Injection