Draft Schedule for Run03-1, 2024

October 7 0800 – October 8 0800



Time

Descriptions

Studiers

SR Status


Monday, October 7, 2024



0900-1000

Install circulator at K4

Yang

No Injection

0900-1000

Test IEX code

Smith

No Beam

0900-1000

Unlock shutters

Wayman/MOM

Zone C AA

0900-1000

Repair thermocouples

Weghorn

Access Zone C

0900-1000

Check magnet serial number

Sun

Access ITS

0900-1000

Connect L1:P0 to scope

Brill

No Injection

0900-1000

Check ITS BPM cables

Erwin

Access ITS

0900-1100

Condition K6

Meyer

No Injection

0900-1100

DCCT measurements

Fors

No Beam

1000-1100

Repair thermocouples

Weghorn

Access Zone B

1000-1200

Investigate K1 instability

Yang

No Injection

1100-1300

H-coll controller

Wang

No beam

1200-1400

Recover SR, i.e. standardize, check tunes, measure response matrix, chromaticity

Ops/Emery

Stored beam & Injection

1300-1500

Adjust and test timing improvements to the SR DCCT trigger (shared beam)

Fors

Stored beam & Injection

1500-1800

BLS setup for operations for 100 mA

Uli, Berenc, Kelly, Fuerst, Lindberg

Stored Beam & Injection

1800-2200

MOFB tests with additional BPMs

Borland

Stored Beam & Limited Injection

1800-2200

Set up higher harmonic gap voltage in PAR

Harkay, Mohsen, Sun

Stored Beam & Limited Injection

2200-2400

LFB tuning

Uli, Kallakuri, Cheng, Emery

Stored Beam & Injection


Tuesday October 8, 2024



0000-0300

LFB tuning

Uli, Kallakuri, Cheng, Emery

Stored Beam & Injection

0300-0400

Test ID intensity optimization software with beam and xray bpm readings

Shang

Stored Beam & No Injection

0300-0600

Injector training (18-06)

Ops

Stored Beam & No Injection

0600-0800

Injector training/prepare for user beam

Ops

Stored beam & Injection