Machine Studies

Schedule for Run03-4, 2024

October 28 0800 – October 29 0800



Time

Descriptions

Studiers

SR Status


Monday, October 28, 2024



0800-1600

MCC-R2 Shutdown

Doktorczyk/Scheck

RF1 and RF2 off and Booster off

0800-0900

Prepare for Zone E Access

OPS/FAC

No Beam

0800-1500

Install AC Line Motor System/Meter in M1 power supply

Puttkammer

No Beam

0800-0900

HCOLL controller chassis update and reboot all camera IOCs

Wang

No Beam

0900-1100

Prepare for Zone A, B, C, and F Access

OPS/FAC

No Beam

0900-1300

Zone E access to install S35 ID and unlock 31ID FE shutter/PSS end to end test

MD Group/SI

No Beam

0900-1100

DCCT Study

Wang

No Beam

0900-1000

Implement swap-out run control in IOC

Arnold

No Beam

0900-1000

Investigate MPS fault reset with IDs in Zone D closed

M. Smith

No Beam

0900-1000

Swap failed amplifier in Sector 38 on mezzanine

Diag group

No Beam

0900-1000

Install heliax cables in Sector 35 on mezzanine

Weghorn

No Beam

1000-1400

Upgrade unipolar PS controller firmware

Kreps

No Beam

1100-1500

Zone A access to repair encoders for 7ID and unlock 2BM FE shutter/PSS end to end tests

MD Group/SI

Zone A AA

1100-1300

Collect vibration data on vacuum chambers in candidate sectors

Preissner Mohsen Emery

Zones ABC AA
Zone F CA

1100-1300

Change pump speed during vibration measurements (in parallel with above)

Bracken (MOM)

Zones ABC AA
Zone F CA

1100-1500

Zone B access to unlock 14ID FE shutter/PSS end to end tests

MD Group/SI

Zone B AA

1100-1500

Zone C access to repair encoders 21ID

MD Group/SI

Zone C AA

1100-1300

Zone F access to remove matching networks and install combiner on bpm

Brill

Zone F CA

1100-1300

Zone F; Check the optical alignment of the 35-BM front end optical transport

Wootton

Zone F CA

1100-1200

Prepare for Linac Access

OPS/FAC

Zones ABC AA
Zone F CA

1200-1300

Linac access to install ferrites on Linac BESOCM

Keane

Zones ABC AA
Zone F CA

1300-1400

Recover Linac from access

OPS/FAC

Zones ABC AA
Zone F CA

1400-1600

Test unipolar power supply firmware updates (if possible)

Kreps

Zones ABC AA
partial time

1500-1700

Recover Storage Ring magnets

OPS/FAC


1600-1700

Recover Booster from MCC shutdown

OPS


1700-1800

Recover Storage Ring beam (140 mA)

Emery

Stored Beam & Injection

1800-2000

Booster tune measurement fix (parasitic)

Calvey Fors Dimonte

Stored Beam & Injection

1800-2100

Optics correction after change in SR conditioning sequence.

Emery Soliday

Stored Beam & Injection

1800-2100

Parasitic measurement of septum leakage field waveform when beam is stored

Borland

Stored Beam & Injection

2000-2400

PAR and booster high charge studies (possible incomplete overlap with stored SR beam at the beginning)

Calvey, Harkay Mohsen

Stored Beam & Injection


Tuesday October 29, 2024



0000-0400

Study MOFB with smaller number of BPMs (160, 80, 40), higher rates, and few singular values for 30 Hz motion correction

Borland, Emery, Chandler, Arnold

Stored Beam & Injection

0400-0800

ID perturbation measurement

Emery Shang

Stored Beam and No Injection

0800-1100

Test slow beam abort (SBA) on IETS

Paskvan

No Beam

0800-1100

DCCT Study #2

Wang

No Beam

0800-1000

Storage Ring Power Supply PEM testing

Berkland/Fystro

No Beam

0900-1100

Move InjTime PAR fundamental upstream of LIST phase shifter.

Fors/Harkay

No Beam and No Injection

1100-1300

Test Booster and Storage Ring injection after PAR fundamental work

Fors

Stored Beam & Injection

1300-2100

Switch LFB between phase sensing using differentiator FIR and energy sensing

Kallakuri Lindberg Emery

Stored Beam & Injection

2100-2400

Ramping current up to 150 mA with BLS tuning by Joel

Emery Fuerst

Stored Beam & Injection





0000-0400

Systematic study of single-bunch lifetime vs BLS voltage.

Borland. Fuerst

Stored Beam and No Injection

0400-0600

160-corrector response matrix with new optics (10 mA)

Emery

Stored Beam and No Injection

0600-0800

Prepare for beamline studies

OPS

Stored Beam & Injection