Draft Schedule for Run03-9, 2024
December 9 0800 – December 11 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, December 9, 2024 |
|
|
0800-1600 |
ID7 bunch length versus BLS voltage |
Borland, Wienands et al |
Stored Beam & Injection |
1600-1800 |
Event 104 for triggering FOK on a scope |
Hong, Iftikhar, Dooling, Grass |
Stored Beam & Injection |
1800-2000 |
FOK study and low-current beam scan at collimators |
Dooling |
Stored Beam & Injection |
2000-0100 |
Software testing for PAR (2 h)+ PAR RF high charge study (3 h) |
Mohsen |
Limited Injection |
|
Tuesday December 10, 2024 |
|
|
0100-0200 |
PAR THz detector testing II |
Wootton, Suzuki |
Limited Injection |
0200-0400 |
Injector training I (18-06) |
Ops |
Limited Injection |
0400-0600 |
Open |
|
Stored Beam & Injection |
|
Start of long intervention |
|
|
0600-0730 |
Shutdown injectors and SR start rack outs |
Ops/FAC |
No Beam |
0730-1030 |
Troubleshoot tunnel thermocouples |
Irwin |
Access Linac |
0730-1030 |
RG2 thyratron troubleshooting |
Puttkammer |
Access Linac |
0730-1130 |
Cable runs, swap FOM card, reboot iocs |
Hong, et al |
No Beam No Injection |
0800-1000 |
Vibration measurements |
Preissner |
Access Zone A |
0800-1000 |
8ID hutch work |
Boron |
No Beam |
0800-1000 |
Test M1/M2 DAQ software |
Paskvan |
No Beam |
0800-1000 |
Upgrade the SR power supplies PLC Controller firmware |
Kreps |
No Beam |
0800-1000 |
IETS timing work |
Fors |
No Beam/No RF |
0800-1200 |
IOC reboots |
Chandler(s) |
No Beam |
0800 |
Reboot sioc2injorch1 |
Arnold |
No Beam |
0900-1100 |
DEEI inspections |
Kishbaugh |
No Impact |
0900-1100 |
Unlock front end shutters |
Wayman, MOM |
Access Zone B & C |
1000-1300 |
Gap minimum measurements |
Wei |
No Beam Zone B secured |
0930-1130 |
LFC measurement |
Vargas |
Access Zone F |
1200 |
Start of SR recovery, e.g. magnet conditioning. |
Ops |
No Beam |
1300-1400 |
Pulse fanout kicker and collect waveforms |
Abid |
No Beam |
1300-1600 |
K2 measurements |
Meyer, ScandiNova |
No Injection |
1300-1500 |
HV Pulser Data |
Paskvan |
No Beam |
|
End of long intervention |
|
|
1600-2000 |
Booster with large momentum offset |
Calvey, Harkay, Fors, Wienands, Mohsen |
Stored Beam & Injection |
1700 |
First beam in SR from intervention? Tune adjustment, etc. |
Emery |
Stored Beam & Injection |
No time |
(06-18) Injector training II. Canceled. |
Ops |
Limited Injection |
2000-2200 |
BTS and booster extraction energy |
Sajaev, Emery |
Stored Beam & Injection |
2200-2400 |
Septum LFC correction IV |
Borland |
Stored Beam & Injection |
|
Wednesday December 11, 2024 |
|
|
0000-0400 |
(18-06) Injector training III |
Ops |
Limited Injection |
0200-0400 |
Open |
|
Stored Beam & Injection |
0400-0600 |
LOCO SR response matrix for reference. Document set-up for beamline operations. |
Emery |
Stored Beam & Injection |
0600-0800 |
Injector training/prepare for user beam |
Ops |
Stored beam and injection |