Machine Studies

Draft Schedule for Run03-9, 2024

December 9 0800 – December 11 0800



Time

Descriptions

Studiers

SR Status


Monday, December 9, 2024



0800-1600

ID7 bunch length versus BLS voltage

Borland, Wienands et al

Stored Beam & Injection

1600-1800

Event 104 for triggering FOK on a scope

Hong, Iftikhar, Dooling, Grass

Stored Beam & Injection

1800-2000

FOK study and low-current beam scan at collimators

Dooling

Stored Beam & Injection

2000-0100

Software testing for PAR (2 h)+ PAR RF high charge study (3 h)

Mohsen

Limited Injection


Tuesday December 10, 2024



0100-0200

PAR THz detector testing II

Wootton, Suzuki

Limited Injection

0200-0400

Injector training I (18-06)

Ops

Limited Injection

0400-0600

Open


Stored Beam & Injection


Start of long intervention



0600-0730

Shutdown injectors and SR start rack outs

Ops/FAC

No Beam

0730-1030

Troubleshoot tunnel thermocouples

Irwin

Access Linac

0730-1030

RG2 thyratron troubleshooting

Puttkammer

Access Linac

0730-1130

Cable runs, swap FOM card, reboot iocs

Hong, et al

No Beam No Injection

0800-1000

Vibration measurements

Preissner

Access Zone A

0800-1000

8ID hutch work

Boron

No Beam

0800-1000

Test M1/M2 DAQ software

Paskvan

No Beam

0800-1000

Upgrade the SR power supplies PLC Controller firmware

Kreps

No Beam

0800-1000

IETS timing work

Fors

No Beam/No RF

0800-1200

IOC reboots

Chandler(s)

No Beam

0800

Reboot sioc2injorch1

Arnold

No Beam

0900-1100

DEEI inspections

Kishbaugh

No Impact

0900-1100

Unlock front end shutters

Wayman, MOM

Access Zone B & C

1000-1300

Gap minimum measurements

Wei

No Beam Zone B secured

0930-1130

LFC measurement

Vargas

Access Zone F

1200

Start of SR recovery, e.g. magnet conditioning.

Ops

No Beam

1300-1400

Pulse fanout kicker and collect waveforms

Abid

No Beam

1300-1600

K2 measurements

Meyer, ScandiNova

No Injection

1300-1500

HV Pulser Data

Paskvan

No Beam


End of long intervention



1600-2000

Booster with large momentum offset

Calvey, Harkay, Fors, Wienands, Mohsen

Stored Beam & Injection

1700

First beam in SR from intervention? Tune adjustment, etc.

Emery

Stored Beam & Injection

No time

(06-18) Injector training II. Canceled.

Ops

Limited Injection

2000-2200

BTS and booster extraction energy

Sajaev, Emery

Stored Beam & Injection

2200-2400

Septum LFC correction IV

Borland

Stored Beam & Injection


Wednesday December 11, 2024



0000-0400

(18-06) Injector training III

Ops

Limited Injection

0200-0400

Open


Stored Beam & Injection

0400-0600

LOCO SR response matrix for reference. Document set-up for beamline operations.

Emery

Stored Beam & Injection

0600-0800

Injector training/prepare for user beam

Ops

Stored beam

and injection