Draft Schedule for Run01-10 2025

April 7 0800 – April 9 0800



Time

Descriptions

Studiers

SR Status


Monday, April 7, 2025



0830-0900

Reboot siocrunctrl2 

Xu

No Beam

0830-1030

Install unipolar standardization script

B. Chandler

No Beam

0830-1030

PS Group work

Puttkammer

No Beam

0830-1030

Test RF-2 digital LLRF on S36C1 with RF on low power

Madden

No Beam

0830-1030

Investigate IETS trigger fiber between MCR and S39 IK rack

Forx

No Beam

0845-0930

5BM PSS End to End test

SI Group

No Beam

0845-1030

Unlock and test shutters at 15ID

McNamara

Access Zone B

0900-1000

PC Gun RF cable mapping

Berenc

Access Linac

0900-1000

Troubleshoot ITS Linac RF interface

Lenner

No Injection

0900-1100

Replace leaking flag actuator

Kishbaugh

Access Linac

0900-1100

Replace leaking flag actuator/Cable ID

Erwin/Diag Group

Access ITS

1000-1200

Calibrate PAR LLRF tuner

Berenc

No Injection

1100-1400

Recover SR & Injectors/test calibration script

Ops/Chandler

Stored Beam & Injection





1200-1600

RG2 beam tune up

Sun

No Injection

1600-2000

RF12 high voltage study

Mohsen

Limited Injection

2000-2400

Booster high charge studies

Calvey Mohsen Shang

Limited Injection


Tuesday April 8, 2025



0000-0400

LFB drive/damp HOM measurements.

Kallakuri

Stored Beam & Injection

0400-0700

Characterize effect of SR magnet cycling on tunes,orbit, etc

Emery

Stored Beam & Injection

0700-1100

Measure kicker timing shift with voltage

Borland Carwardine

Stored Beam & Injection

1100-1300

Measure DA using IK1 including collection of SPARK data and kicker timing feedforward

Borland

Stored Beam & Injection

1300-1500

Injector training (08-18)

Ops

Limited Injection

1500-1800

RG2 magnets scan data collect for hysteresis study


Shang, Mohsen, Sun

Stored Beam & Injection

1800-2000

SR Injection Efficiency Optimization with knobs

Shang, Emery

Stored Beam & Injection

2000-2200

open


Stored Beam & Injection

2200-2400

Injector training (18-06)

Ops

Limited Injection


Wednesday April 9, 2025



0000-0300

Setup 48 bunches, fine tune injection trajectory, measure chromaticity, etc.

Emery

Stored Beam & Injection

0300-0600

Correct coupling for reference

Emery

Stored Beam & Injection

0600-0800

Recover SR systems/prepare for user beam

Ops

Stored Beam and Injection