Machine Studies
Draft Schedule for Run01-2, 2025
February 3 0800 – February 4 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, February 3, 2025 |
|
|
0800-0900 |
Test remote reset of BESOCM |
Keane |
No Injection |
0800-1000 |
Check K4 VSWR levels |
Yang |
No Injection |
0800-1000 |
Reboot PSAGG soft iocs |
Shoaf |
No Beam |
0800-1000 |
Test PS aggregator rest script |
E. Chandler |
No Beam |
0800-1000 |
Update IETS firmware and Reboot sioc2accumloss |
Fors |
No Beam/No Injection |
0800-1000 |
Replace B3C5V GESPAC |
Puttkammer |
No Injection |
0800-1000 |
Unstick quadrupoles |
Kreps |
No Beam |
0830-1030 |
Evaluate IDVC location in S08 |
Wei |
Access Zone A |
1000-1200 |
(06-18) Injector training |
Ops |
Limited Injection |
1200-1400 |
SR stored beam checkout, response matrix measurement |
Emery |
Stored beam & injection |
1400-1800 |
Bunch length measurement from button BPM signal. Single bunch |
Cheng |
Stored Beam & Injection |
1400-1800 |
PAR Harmonic high voltage study. Parallel with above |
Mohsen, Calvey |
Stored Beam & Injection |
1800-2200 |
Continue to condition with beam to 200 mA with ID gaps closed |
Emery Berenc |
Stored beam & injection |
|
|
|
|
2200-0200 |
Orbit feedback studies to simulate local FOFB with MOFB |
Carwardine, Kallakuri |
Stored Beam & Injection |
|
Tuesday February 4, 2025 |
|
|
0200-0600 |
FOK y-displacement measurement in pinger mode |
Dooling |
Stored Beam & Injection |
0600-0800 |
Injector training/prepare for user beam |
Ops |
Stored beam & injection |
|
|
|
|