Machine Studies

Draft Schedule for Run01-6 2025

March 3 0800 – March 4 0800



Time

Descriptions

Studiers

SR Status


Monday, March 3, 2025



0800-1230

RG1 study

Yin-e

K5 off/ No Injection

0800-1100

LLRF cable making at K5

Yawei

K5 off/ No Injection

0900-1000

Enable S40 HCOLL motor

Grass

No Beam

0900-1000

Undo MPS changes

Smith

No Beam

0900-1100

Investigate BTS:AB trips

Kreps/Jordan

Limited Injection

0900-1100

Unstick SR sector 40 Cab1 PS4 (S40A:S1)

Vargas

No Beam

0900-1100

Investigate B3C5V (CPS OT)

Puttkammer

Limited Injection

0900-1100

Troubleshoot BLS dewar level problem

Furst/McDonald

No Beam

1000-1100

Measure MPS RF mute FOK delay

Dooling

No Beam





1230-1600

FOFB (fill to 200 mA)

Carwardine Kallakuri

Limited injection

1300-1700

PAR RF12 high voltage

Mohsen Calvey

Limited injection

1700-1800

Injector training (08-18)

Ops

Limited Injection

1800-2000

Booster high charge

Calvey Mohsen

Limited injection

2000-2100

RF noise suppression effectiveness data at I < 200 mA

Berenc Emery

Stored Beam and Injection

2100-2300

FOPK y-displacement (I < 10 mA)

Dooling

Stored Beam and Injection

2300-2400

Injector training (18-06)

Ops

Limited Injection


Tuesday March 4, 2025



0000-0400

Corrected SR lattice for first set of new sextupoles Borland provided

Emery

Stored Beam and Injection

0400-0600

Look at instability of injected bunch at 200 mA

Emery

Stored Beam and Injection

0600-0800

Recover SR systems/prepare for user beam

Ops

Stored Beam and Injection