Machine Studies

Draft Schedule for Run01-9 2025

March 24 0800 – March 25 0800



Time

Descriptions

Studiers

SR Status


Monday, March 24, 2025



0800-1100

Booster console testing

Fystro/Sas-Pawlik

Limited Injection

0830-1030

Verify wiring at 31ID

Boron

No Beam

0830-1030

Upgrade S38:39 PLC firmware

Ruan

No Beam

0830-1030

Reboot sioc2btc

Fors

No Beam

0900-1000

Assess Sector 8 for installation

Wei

Access Zone A

0900-1300

6ID vacuum investigation

Clute

Access Zone A

0930-1130

Verify shutters and FEEPS at 28ID

McNamara

Access Zone D

1000-1100

ALD tour

Sajaev/Chapon

Access Zone A

1100-1300

Fix BTS:BB CT

Jordan

No Injection

1100-1300

linac rf waveguide switching test

Sun

No Injection

1100-1300

Linac RF reboot and then conditioning for eventual 450 MeV

Meyer

No Injection 11-12

Limited Injection after

1330-1630

Recover SR and Injectors

Ops

Limited Injection





1500-1900

PAR RF12 high voltage

Mohsen

Limited Injection

1900-2100

test the SR injection efficiency optimizer

Shang Emery

Stored Beam and Injection

2100-2200

Adjust Booster extraction energy by +2e-3 relative

Emery Fors

Stored Beam and Injection

2200-2400

horizontal DA using an injection kicker

Borland

Stored Beam and Injection

4 h

RG1

Sun

No Injection


Tuesday March 25, 2025



0000-0400

LFB studies, grow/damp and HOM measurements

Kallakuri

Stored Beam and Injection

0400-0600

Setup 48 bunches

Emery

Stored Beam and Injection

0600-0800

Recover SR systems/prepare for user beam

Ops

Stored Beam and Injection