Machine Studies
Draft Schedule for Run02-3, 2025
June 16 0800 – June 18 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, June 16, 2025 |
|
|
0800-1000 |
PAR console testing |
Fystro/Urban |
Limited Injection |
0830-1130 |
Update FOFB bipolar firmware/change unipolar IP addresses |
Kreps |
No Beam |
0800-1000 |
Update TBT IOCs |
E. Chandler |
No Beam |
0900-1100 |
Replace the DOSFET sensor in S01 |
Wei |
Access Zone A |
1000-1300 |
Change Linac reference timing |
Hong |
Linac RF down |
1000-1300 |
BTS corrector fuse upgrade |
Jordan |
No Injection |
1000-1300 |
Replace PAR kicker control power |
Puttkammer |
No Injection |
1000-1200 |
Adjust PAR RF-12 drive |
Smith |
No Injection |
1100-1300 |
SR magnet conditioning |
Ops |
No Beam |
1100-1400 |
Test SR kicker firmware |
Paskvan |
No beam |
|
|
|
|
1300-1700 |
450 MeV linac setup and perhaps PAR/booster |
Yine, Mohsen |
Limited Injection |
1700-1800 |
SR beam check and test 10 bpm per sector MOFB (can spill over to next time slot) |
Emery |
Stored beam & injection |
1800-2000 |
Injector training (18-06) |
Ops |
Limited Injection |
2000-0200 |
Low-beta x/y lattice commissioning (conditioning could occur in previous time slot) |
Borland Emery |
Stored beam & injection |
|
Tuesday June 17, 2025 |
|
|
0200-0600 |
|
|
|
0600-0800 |
Injector training (06-18) |
Ops |
Limited Injection |
0800-1100 |
Booster console testing |
Fystro/Sas-Pawlik |
Limited Injection |
1100-1400 |
Test the linac charge optimization with degauss |
Shang |
Limited Injection |
1400-1600 |
TCAV Longitudinal Phase-Space Measurements |
Wootton Suzuki |
Limited Injection |
1600-2000 |
Timing scans with single bunch; Grow/damp measurements |
Kallakuri |
Stored beam & injection |
2000-2200 |
Injector training (18-06) |
Ops |
Limited Injection |
2200-0000 |
|
|
|
|
Wednesday June 18, 2025 |
|
|
0000-0400 |
|
|
|
0400-0600 |
Set up SR for operations |
Emery |
Stored beam & injection |
0600-0800 |
Injector training/prepare for user beam |
Ops |
Stored beam & injection |