Machine Studies
Draft Schedule for Run02-5, 2025
July 4 0000 – July 8 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Friday, July 4, 2025 |
|
|
0000-0005 |
Reboot siocrunctrl2 and sioc2aop1 |
Ops |
Stored beam & injection |
0000-0400 |
SR beam decay |
Diag group |
Stored beam & injection |
0800-1000 |
Tune BLS for 130 mA, any pattern with somewhat more than 48 bunches |
Berenc |
Stored beam & injection |
1000-1200 |
Checkout SR Bpm offset measurement, 10 mA |
Emery |
Stored beam & injection |
1200-1600 |
BTS images |
Xu |
Stored beam & Limited injection |
1200-1600 |
One bunch SR beam measurements |
Weixing |
Stored beam & Limited injection |
1600-1800 |
Operator training (08-18) |
Ops |
Limited Injection |
1800-2000 |
Injector training (18-06) |
Ops |
Limited Injection |
2000-2400 |
SR Bpm offset measurement, 10 mA |
Emery Ops |
Stored beam & injection |
|
Saturday, July 5, 2025 |
|
|
0000-0400 |
|
|
Stored beam & injection |
0400-0700 |
|
|
Stored beam & injection |
0700-0900 |
Linac setup tool testing |
Borland |
Stored beam & No injection |
0900 |
Inject 130 mA, any pattern (say 216 bunches) |
Ops |
Stored beam & injection |
0900-1600 |
f_s measurement with beam decay, 130 mA |
Kallakuri |
Stored beam & No injection |
0900-1600 |
Linac, PAR, Booster high charge |
Sun, Mohsen, Calvey |
Stored beam & No injection |
1600-1800 |
Operator training (08-18) |
Ops |
Limited Injection |
1800-2000 |
SR training (18-06) |
Ops |
Stored beam & injection |
2000-2400 |
Transverse instability measurements |
Lindberg, Emery, Dick |
Stored beam & injection |
|
Sunday, July 6, 2025 |
|
|
0000-0400 |
BTS response measurement |
Sajaev |
Stored beam & injection |
0400-0800 |
|
|
Stored beam & injection |
0800-1000 |
ID gap FF with new python version |
Shang, Emery |
Stored beam & injection |
1000-1600 |
Tune and other magnet cycling for hysteresis error measurement |
Chenran, Emery |
Stored beam & injection |
1600-1800 |
Operator training (08-18) |
Ops |
Limited Injection |
1800-2000 |
SR training (18-06) |
Ops |
Stored beam & injection |
2000-2400 |
LB+ cross-bar switching on/off testing |
Cheng |
Stored beam & injection |
|
Monday, July 7, 2025 |
|
|
0000-0400 |
Other Bpm study |
Cheng |
Stored beam & injection |
0400-0600 |
|
|
Stored beam & injection |
0600-0800 |
Prepare for accesses |
Ops and FAC |
No Beam |
0800-1000 |
Replace leaking flag actuator |
Kisbaugh |
Access Linac |
0800-1000 |
Map video cables for PC gun and laser |
Dooling |
Access Linac |
0800-0900 |
Swap L5:SC2:VL |
PS group |
No Injection |
0800-1000 |
Connect external CT to L3:QM3 |
PS group |
No Injection |
0800-1000 |
Investigate P1K thyratron |
Puttkammer |
Access PAR |
0800-1000 |
Upgrade Zone B PLC program |
Ruan |
No Beam |
0800-1000 |
Investigate S01AQ3 60hz noise |
Kreps |
No Beam |
0800-1000 |
RF wave-guide switch from RF1,2 & 5 to RF3,4 & 5; |
RF group |
No Beam |
0800-0900 |
Update and restart SR magnet supplies |
Brendan |
No beam |
0830-1000 |
34ID PSS commissioning/end to end test |
SI Group |
Access Zone E |
0900-1000 |
Replace faled amplifier at S38 mezzanine |
Kisbaugh |
No Beam |
0900-1000 |
Check dosfet cable at S12 |
Wei |
Access Zone B |
0900-1000 |
Add QR label at S14 |
Weghorn |
Access Zone B |
0930-1030 |
Check water flow at IEX |
Wright |
Access Zone D |
1000-1030 |
ITS LDRD tour |
Sun |
Access ITS |
1030-1300 |
Prepare the SR magnets |
Ops |
No beam |
1030-1300 |
Check-out RF3 under power |
RF group |
No Beam |
1300-1330 |
Test “Align P0” medm button, one bunch injected |
Berkland |
Stored beam & injection |
1330-1600 |
Slow beam abort |
Paskvan |
No Beam |
1330-1600 |
K1-based swap-out permissive testing. No beam required |
Borland |
No beam |
1330-1600 |
Open to any injector beam tests |
Mohsen, Calvey |
No beam |
1600-1800 |
Operator training (08-18) |
Ops |
Limited Injection |
1800-2000 |
SR training (18-06) |
Ops |
Stored beam & injection |
2000-2400 |
Final RF3 noise suppression and BLS tuning to perhaps > 130 mA |
Berenc |
Stored beam & injection |
|
Tuesday, July 8, 2025 |
|
|
0000-0200 |
LFP checkout |
Kallakuri |
Stored beam & injection |
0200-0600 |
Final setup for 48 bunches |
Emery |
Stored beam & injection |
0600-0800 |
Injector training/prepare for user beam |
Ops |
Stored beam & injection |