Machine Studies

Draft Schedule for Run02-7, 2025

July 21 0800 – July 23 0800



Time

Descriptions

Studiers

SR Status


Monday, July 21, 2025



0800-0830

Reboot iocrf5mon

Ops

Limited Injection

0800-1000

Linac console testing

Fystro/Lawson

Limited Injection

0800-1000

S3 &4 FOFB testing

Carwardine

No Beam

0830-0900

Reboot sioc2injorch1

Fors

No Beam

0830-1000

Adjust BTS BESOCM

Keane

No Injection

0830-1030

Upgrading PLC program for SR Raw Power Supplies in Zone B and C.

Ruan

No Beam

0830-1130

Check FOK scope and DCCT studies

Grass

No Beam

0830-1300

Booster extraction troubleshooting

Madden

No Injection/ Possible Booster Access

0830-1030

IK waveform monitoring. Needs kicker magnets on.

Paskvan

No beam

0900-1100

Connect streak camera

Wootton

No Beam

0900-1300

Fix ID taper at S19

Wei

Access Zone C

0930-1100

Verify BPM serial numbers

Weghorn

Access Zone D

1000-1100

RF shutter inspection

MOM

Access ITS

1030-1100

Test LACIS E-stop

Nguyen

Access Linac

1130-1400

PAR console testing

Urban/Fystro

Limited Injection

1400-1630

Recover SR and Injectors

Ops/FAC/HP

Limited injection

1530-1630

Set up reference tunes, coupling, chromaticities for later DA measurement

Emery

Stored beam & injection





1630-2030

fast orbit feedback studies I

Carwardine, Kallakuri et al

Stored beam & injection

2030-2200

Injector training (18-06)

Ops

Limited Injection

2200-0200

DA measurements with injection kicker IK1

Borland

Stored beam & injection


Tuesday July 22, 2025



0200-0400

drifting BPMs" with crossbar switch

Cheng

Stored beam & injection

0400-0600




0600-0800

Hysteresis tests related to the K1 permissive

Emery, Chenran

Stored beam & injection

0800-1200

test collect gap FF data script

Shang

Stored beam & injection

0800-1100

test the streak camera in parallel with above

Wootton

Stored beam & injection

1200-1600

fast orbit feedback studies II

Carwardine, Kallakuri et al

Stored beam & injection

1600-1800

Injector training (06-18)

Ops

Limited Injection

1800-2000

Injector training (18-06)

Ops

Limited Injection

2000-2230

K1 permissive

Borland

Stored beam & injection

2230-0030

Momentum acceptance measurements from rf scan, S40 RF off.

Borland, Emery

Stored beam & injection


Wednesday July 23, 2025



0030-0400

measure the tune shift with charge, and more

Lindberg, Emery, Dick

Stored beam & injection

0400-0600

Set up SR for operations

Emery

Stored beam & injection

0600-0800

Injector training/prepare for user beam

Ops

Stored beam & injection