Machine Studies
Draft Schedule for Run02-8, 2025
July 28 0800 – July 29 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, July 28, 2025 |
|
|
0800-0900 |
Script / screen checkout |
Berkland |
Stored Beam and Injection |
0900-0930 |
Update DCCT and fokscope iocs |
Grass |
No Beam |
0900-1000 |
Start DAQ aggregator |
E. Chandler |
No Beam |
0900-1000 |
Update USPC ioc |
B. Chandler |
No Beam |
0930-1130 |
Troubleshoot L3:QM3 |
PS Group |
No Injection |
0930-1130 |
Update SRPS Raw firmware |
Ruan |
No Beam |
1000-1100 |
IETS reboot plus RF system down and then up |
Fors, rf group |
No beam |
1000-1400 |
Fix 4ID taper |
Wei |
Access Zone A |
1200-1400 |
Verify the new SR unipolar PS conditioning around this time before whole ring conditioning |
Emery |
Limited injection |
1400-1530 |
Recover SR systems |
Ops/FAC |
Limited injection |
|
|
|
|
1200-1600 |
Booster on-momentum operation. Part I: The Timing |
Calvey |
No Beam nor injection |
1200-1600 |
SR kicker waveform monitoring |
Paskvan |
No Beam nor injection |
1600-1800 |
Booster on-momentum operation. Part II: Injection into SR |
Calvey, Emery |
Stored Beam and Injection |
|
|
|
|
1800-2000 |
Operator training (18-08) |
Ops |
Limited injection |
2000-2200 |
Momentum aperture |
Borland |
Stored beam & injection |
2200-0200 |
FOFB |
Carwardine Kallakuri at al |
Stored beam & injection |
|
Tuesday July 29, 2025 |
|
|
0200-0500 |
BTS response measurement |
Sajaev |
Stored beam & injection |
0500-0600 |
SR set up |
Emery |
Stored beam & injection |
0530-0600 |
SR with drifting orbit |
Emery, Cheng |
Stored beam & injection |
0600-0800 |
Injector training/prepare for user beam |
Ops |
Stored beam & injection |