Machine Studies
Draft Schedule for Run03-10, 2025
November 17 0800 – November 18 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, November 11, 2025 |
|
|
0830-0930 |
Replace strobe for K1 |
Meyer |
No Injection |
0830-1000 |
PEM testing/ ioc reboots |
Fystro/Paskvan |
Limited injection |
0830-1000 |
S03 FOFB synthetic measurements |
Cheng |
No Beam |
0830-1030 |
PAR RF-1 digital LLRF adjustments |
Berenc |
No Injection |
0830-1030 |
Update firmware |
Kreps |
No Beam |
0900-1100 |
Take data on pulsing S:IS1 |
Puttkammer |
No Beam |
0900-1100 |
Test slow-MPS dump (kicking SR kickers and DK) |
Paskvan |
No Beam |
0900-1200 |
Laser alignment |
Dooling |
Access Linac |
0930-1130 |
Replace thermocouples |
Weghorn |
Access Zone D |
1000-1200 |
Test K6 chassis |
Yang |
Limited injection |
1130-1300 |
SR magnet recovery |
Ops |
Limited injection |
1230-1530 |
Linac console testing |
Lawson/Fystro |
Limited injection |
|
|
|
|
|
|
|
|
1530-1600 |
Orbit with S:M1 with lowered set point with I= 2 mA; Punch down S28BV8; Test some BTS one-iteration trajectory correction buttons |
Emery |
Limited Injection |
1600-1800 |
PAR RF fundamental |
Mohsen |
Limited Injection |
|
|
|
|
1800-2000 |
Injector training (18-06) |
Ops |
Limited Injection |
2000-2400 |
DA optimization |
Borland, Kuklev, Emery |
Stored beam & injection |
|
Tuesday November 18, 2025 |
|
|
0000-0400 |
HOM search |
Kallakuri, Emery |
Stored beam & injection |
0400-0500 |
Open |
|
Stored beam & injection |
0500-0600 |
SR set up |
Emery |
Stored beam & injection |
0600-0800 |
Injector training/prepare for user beam |
Ops |
Stored beam & injection |