0800-0830

Measure response matrix 130 mA, 9 mA 48 bunches, ID gaps closed

Ops

Stored beam & injection

0830-0900

Prepare for accesses

Ops

No Beam

0900-1000

Update PAR RF-12 SSA firmware

DiMonte

No Injection

0900-1000

Update DAQ IOCs

E. Chandler

No Beam

0900-1000

Install Libera photon device cabling

Brill

No Impact

0900-1000

Troubleshoot 35BM XBPM-1/configuration pictures

Wooton/Clute

Access Zone F

0900-1200

Install IDVC support at S35.

Donnelly

Access Zone E

0900-1200

FOFB sector 09 cable installations

Shoaf

No Beam

0930-1200

PC gun laser alignment

Dooling

Access Linac

1000-1100

Connect vibration monitoring equipment

Preissner

Access Zones A & D

1100-1200

Recover SR magnets

Ops

No Beam

1100-1200

Test run S:IS1

Abid

No Beam

1100-1200

Remove EDM module at K5 and trip test K6

Yang

No Injection

1100-1300

Test run P:1K

Puttkammer

Limited Injection

1000-1300

IES software updates (FID pulsers on – wait for Zone F closure) plus tests

Grass, Paskvan, Fors

No Beam

1300-1400

SR beam checkout

Emery

Stored beam & injection

1400-1800

FOFB (parasitic to BLS)

Carwardine

Stored beam & injection

1400-1800

BLS Quench investigations (130 mA to 70 mA decays)

Fuerst, Kelly, Berenc

Stored beam & injection

1400-1800

Streak camera measurement with various BLS tunings (parasitic to above)

Wootton

Stored beam & injection

1800


Fill once 216 bunch pattern 120 mA for FOFB

Ops

Stored beam & Limited injection

1800-2000

Injector training (18-06)

Ops

Limited Injection

2000-2400

LFB studies with Dimtel engineer

Kallakuri

Stored beam & injection


Tuesday December 09, 2025



0000-0500

RG1

Sun

Limited Injection

0500-0700

PAR RF12 Feed forward (before Booster high charge)

Mohsen, Xu

Limited Injection

0700-0800

LTP controllaw

Mohsen, Xu

Limited Injection

0800-1400

SR console testing

Berkland/Hotham/Ronzhin

Limited availability

1400

Fill 10 mA with 2 nC bunches for SR FOFB study in parallel to below

Ops

Stored beam & Limited injection

1400-1800

Booster high charge studies

Calvey, Mohsen

Limited injection

1800-2000

Injector training (18-06)

Ops

Limited Injection

2000-2400

LFB studies with Dimtel engineer

Kallakuri

Stored beam & injection


Wednesday December 10, 2025



0000-0500

Optimization of lifetime and efficiency in operations lattice

Borland, Kuklev,Emery

Stored beam & injection

0500-0600

Set up SR for operations

Emery

Stored beam & injection

0600-0800

Injector training/prepare for user beam

Ops

Stored beam & injection