Draft Schedule for Run03-12, 2025
December 08 0800 – December 09 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, December 08, 2025 |
|
|
0800-0830 |
Measure response matrix
|
Ops |
Stored beam & injection |
0830-0900 |
Prepare for accesses |
Ops |
No Beam |
0900-1000 |
Update PAR RF-12 SSA firmware |
DiMonte |
No Injection |
0900-1000 |
Update DAQ IOCs |
E. Chandler |
No Beam |
0900-1000 |
Install Libera photon device cabling |
Brill |
No Impact |
0900-1000 |
Troubleshoot 35BM XBPM-1/configuration pictures |
Wooton/Clute |
Access Zone F |
0900-1200 |
Install IDVC support at S35. |
Donnelly |
Access Zone E |
0900-1200 |
FOFB sector 09 cable installations |
Shoaf |
No Beam |
0930-1200 |
PC gun laser alignment |
Dooling |
Access Linac |
1000-1100 |
Connect vibration monitoring equipment |
Preissner |
Access Zones A & D |
1100-1200 |
Recover SR magnets |
Ops |
No Beam |
1100-1200 |
Test run S:IS1 |
Abid |
No Beam |
1100-1200 |
Remove EDM module at K5 and trip test K6 |
Yang |
No Injection |
1100-1300 |
Test run P:1K |
Puttkammer |
Limited Injection |
1000-1300 |
IES software updates (FID pulsers on – wait for Zone F closure) plus tests |
Grass, Paskvan, Fors |
No Beam |
1300-1400 |
SR beam checkout |
Emery |
Stored beam & injection |
1400-1800 |
FOFB (parasitic to BLS) |
Carwardine |
Stored beam & injection |
1400-1800 |
BLS Quench investigations (130 mA to 70 mA decays) |
Fuerst, Kelly, Berenc |
Stored beam & injection |
1400-1800 |
Streak camera measurement with various BLS tunings (parasitic to above) |
Wootton |
Stored beam & injection |
1800
|
Fill once 216 bunch pattern 120 mA for FOFB |
Ops |
Stored beam & Limited injection |
1800-2000 |
Injector training (18-06) |
Ops |
Limited Injection |
2000-2400 |
LFB studies with Dimtel engineer |
Kallakuri |
Stored beam & injection |
|
Tuesday December 09, 2025 |
|
|
0000-0500 |
RG1 |
Sun |
Limited Injection |
0500-0700 |
PAR RF12 Feed forward (before Booster high charge) |
Mohsen, Xu |
Limited Injection |
0700-0800 |
LTP controllaw |
Mohsen, Xu |
Limited Injection |
0800-1400 |
SR console testing |
Berkland/Hotham/Ronzhin |
Limited availability |
1400 |
Fill 10 mA with 2 nC bunches for SR FOFB study in parallel to below |
Ops |
Stored beam & Limited injection |
1400-1800 |
Booster high charge studies |
Calvey, Mohsen |
Limited injection |
1800-2000 |
Injector training (18-06) |
Ops |
Limited Injection |
2000-2400 |
LFB studies with Dimtel engineer |
Kallakuri |
Stored beam & injection |
|
Wednesday December 10, 2025 |
|
|
0000-0500 |
Optimization of lifetime and efficiency in operations lattice |
Borland, Kuklev,Emery |
Stored beam & injection |
0500-0600 |
Set up SR for operations |
Emery |
Stored beam & injection |
0600-0800 |
Injector training/prepare for user beam |
Ops |
Stored beam & injection |