Draft Schedule for Run03-13, 2025
December 15 0800 – December 16 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, December 15, 2025 |
|
|
0800-0830 |
Measure response matrix 9 mA 48 bunches, ID gaps closed. Injection not needed. |
Emery |
Stored beam |
0800-1100 |
Linac console testing |
McBride/Fystro |
Limited Injection |
0830-0900 |
Prepare for access zone F |
Ops |
Access Zone F |
0830-1030 |
BPM synthetic data and check the data flow to the S09 FOFB controller. No beam. |
Cheng |
Access Zone F |
0830-1030 |
Test L1:CM1 |
Keane |
Access Zone F |
0830-1030 |
Test Volt Monitor Chassis at K6 |
Yawei |
Access Zone F |
0900-1000 |
Mount x-ray monitor on BLS |
Fuerst/Kelly |
Access Zone F |
0900-1100 |
Test BPM synthetic data and FOFB |
Weixing |
No Beam |
1000 |
Close Zone F |
Ops |
No Beam |
1100-1400 |
SR console testing |
Berkland/Sas-Pawlik |
No Beam |
1100-1400 |
Test SR pulsers. no beam, say during SR magnet conditioning |
Paskvan |
Parasitic/Coordinated with MCR console test |
1100-1400 |
Test run Zone F for noise measurements |
Kreps |
Parasitic/Coordinated with MCR console test |
1100-1400 |
Adjust RF3 phase loops to have more range. No beam. |
Madden |
Parasitic/Coordinated with MCR console test |
|
|
|
|
1400-1500 |
SR beam checkout |
Emery |
Stored beam & injection |
1500-1700 |
BLS Quench investigations (various tunings as well) |
Fuerst, Kelly, Berenc |
Stored beam & injection |
1700-2100 |
HOM investigations |
Kallakuri |
Stored beam & injection |
1700-2100 |
PAR streak camera, parasitic to stored beam of above |
Osama |
Stored beam & injection |
1700-2100 |
S09 FOFB with beam. Parasitic. |
Cheng |
Stored beam & injection |
2100-0100 |
RG1. Need scope from diag group. Fill ring to 10 mA, 2 nC bunches for continued parasitic studies. |
Sun |
Stored beam & Limited Injection |
2100-0100 |
S03 FOFB with beam. Parasitic. |
Carwardine |
Stored beam & injection |
|
Tuesday December 09, 2025 |
|
|
0100-0600 |
Optimization of lifetime and efficiency with hysteresis control. Need sextupole conditioning at end. |
Borland, Kuklev |
Stored beam & injection |
0600-0800 |
Injector training/prepare for user beam |
Ops |
Stored beam & injection |