Machine Studies

Draft Schedule for Run03-2, 2025

September 22 0800 – September 23 0800



Time

Descriptions

Studiers

SR Status


Monday, September 22, 2025



0800-1000

FOFB firmware update

Carwardine

No Beam

0800-1000

Troubleshoot M1 AC unbalancing

Puttkammer

No Beam

0800-1000

Replace fan in S21 cabinet 2 and BPECMS SPI cable in S1

Vargas

No Beam

0800-0900

Connect cable at RF-1

Yang

No Beam

0800-1000

RF1 RF3 MPS validation (no beam needed, I think). This include waveguide switching. Revert to RF2 and RF4 afterwards.

RF group, Smith

No Beam

0900-1000

Test the TRIG&INTLK module at K6

Yang

No Injection

0900--1100

Fix 16ID Revolver issuer

Donnelly

Access Zone B

1130-1300

Recover SR systems

Ops/FAC

Limited injection

1300-1600

Check tunes after various magnet conditionings, in particular M1

Emery/Xu

Stored beam & injection

1600-1800

Operator training (08-18).

Ops

Limited injection

1800-2000

Injector training (18-06)

Ops

Limited Injection

2000-2200

Adjust collimator positions, particularly for S01

Borland, Emery

Stored beam & injection

2200-0200

FOFB

Carwardine Kallakuri

Stored beam & injection


Tuesday September 23, 2025



0200-0400

RF conditioning

Ops

Stored beam & injection

0400-0600

SR set up

Emery

Stored beam & injection

0600-0800

Injector training/prepare for user beam

Ops

Stored beam & injection