Machine Studies
Draft Schedule for Run03-2, 2025
September 22 0800 – September 23 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, September 22, 2025 |
|
|
0800-1000 |
FOFB firmware update |
Carwardine |
No Beam |
0800-1000 |
Troubleshoot M1 AC unbalancing |
Puttkammer |
No Beam |
0800-1000 |
Replace fan in S21 cabinet 2 and BPECMS SPI cable in S1 |
Vargas |
No Beam |
0800-0900 |
Connect cable at RF-1 |
Yang |
No Beam |
0800-1000 |
RF1 RF3 MPS validation (no beam needed, I think). This include waveguide switching. Revert to RF2 and RF4 afterwards. |
RF group, Smith |
No Beam |
0900-1000 |
Test the TRIG&INTLK module at K6 |
Yang |
No Injection |
0900--1100 |
Fix 16ID Revolver issuer |
Donnelly |
Access Zone B |
1130-1300 |
Recover SR systems |
Ops/FAC |
Limited injection |
1300-1600 |
Check tunes after various magnet conditionings, in particular M1 |
Emery/Xu |
Stored beam & injection |
1600-1800 |
Operator training (08-18). |
Ops |
Limited injection |
1800-2000 |
Injector training (18-06) |
Ops |
Limited Injection |
2000-2200 |
Adjust collimator positions, particularly for S01 |
Borland, Emery |
Stored beam & injection |
2200-0200 |
FOFB |
Carwardine Kallakuri |
Stored beam & injection |
|
Tuesday September 23, 2025 |
|
|
0200-0400 |
RF conditioning |
Ops |
Stored beam & injection |
0400-0600 |
SR set up |
Emery |
Stored beam & injection |
0600-0800 |
Injector training/prepare for user beam |
Ops |
Stored beam & injection |