Machine Studies
Draft Schedule for Run03-3, 2025
September 30 0800 – October 1 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, September 30, 2025 |
|
|
0830-1030 |
K6 interlock module testing |
Yang |
No Injection |
0830-0930 |
Troubleshoot L4 water skid flow meter |
Wright |
No Injection |
0830-1030 |
PAR RF testing |
Smith |
No Injection |
0830-1000 |
Troubleshoot PSR02 water switch |
Wright |
No Beam |
0830-1030 |
M1 AC imbalance investigation |
Rafael |
No Beam |
0830-1030 |
Update firmware |
Kreps |
No Beam |
0830-1230 |
IETS. Decoherence trigger investigation. May need to bring down SR RF systems |
Paskvan. Fors. RF group |
No Beam |
0900-1100 |
Fix thermocouples |
Weghorn |
Access Zone C |
0930-1030 |
Connect 136mHz RF cable |
Yang |
No Beam |
0930-1030 |
LFC trigger checkout without beam |
Hong |
|
1100-1300 |
Recover SR magnets |
Ops |
Limited Injection |
1300-1500 |
LFC checkout with beam |
Borland/Hong |
Stored beam & injection |
1500-1600 |
RF cavity conditioning I (increase stored current) |
Emery/RF group |
Stored beam & injection |
1500-1600 |
Check the CBLM signals on a oscilloscope (need incidental injection) |
Weixing |
Stored beam & injection |
1600-1800 |
Operator training (08-18) |
Ops |
Limited injection |
1800-2000 |
Injector training (18-06) |
Ops |
Limited Injection |
2000-2100 |
4 second injector enable |
Calvey |
Stored beam & injection |
2100-2300 |
Collimator position verification (3 nC stored) |
Borland |
Stored beam & injection |
2300-0400 |
RF cavity conditioning II (increase stored current) |
Emery/RF group |
Stored beam & injection |
|
Wednesday October 1, 2025 |
|
|
0400-0600 |
SR set up |
Emery |
Stored beam & injection |
0600-0800 |
Injector training/prepare for user beam |
Ops |
Stored beam & injection |