Machine Studies

Draft Schedule for Run03-3, 2025

September 30 0800 – October 1 0800



Time

Descriptions

Studiers

SR Status


Tuesday, September 30, 2025



0830-1030

K6 interlock module testing

Yang

No Injection

0830-0930

Troubleshoot L4 water skid flow meter

Wright

No Injection

0830-1030

PAR RF testing

Smith

No Injection

0830-1000

Troubleshoot PSR02 water switch

Wright

No Beam

0830-1030

M1 AC imbalance investigation

Rafael

No Beam

0830-1030

Update firmware

Kreps

No Beam

0830-1230

IETS. Decoherence trigger investigation. May need to bring down SR RF systems

Paskvan. Fors. RF group

No Beam

0900-1100

Fix thermocouples

Weghorn

Access Zone C

0930-1030

Connect 136mHz RF cable

Yang

No Beam

0930-1030

LFC trigger checkout without beam

Hong


1100-1300

Recover SR magnets

Ops

Limited Injection

1300-1500

LFC checkout with beam

Borland/Hong

Stored beam & injection

1500-1600

RF cavity conditioning I (increase stored current)

Emery/RF group

Stored beam & injection

1500-1600

Check the CBLM signals on a oscilloscope (need incidental injection)

Weixing

Stored beam & injection

1600-1800

Operator training (08-18)

Ops

Limited injection

1800-2000

Injector training (18-06)

Ops

Limited Injection

2000-2100

4 second injector enable

Calvey

Stored beam & injection

2100-2300

Collimator position verification (3 nC stored)

Borland

Stored beam & injection

2300-0400

RF cavity conditioning II (increase stored current)

Emery/RF group

Stored beam & injection


Wednesday October 1, 2025



0400-0600

SR set up

Emery

Stored beam & injection

0600-0800

Injector training/prepare for user beam

Ops

Stored beam & injection