Machine Studies
Draft Schedule for Run03-4, 2025
October 6 0800 – Ocotber 7 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, October 6, 2025 |
|
|
0800-0830 |
RF “micro conditioning with beam” |
OPS |
Current increase at 2 min intervals |
0900-1100 |
Laser alignment |
Dooling |
Access Linac |
0900-1000 |
BTS sigma matrix code test |
C. Xu |
No beam |
0900-1000 |
Update SR bpm offsets |
Emery/Cheng/Dick |
No beam |
0930-1030 |
Replace blower |
MOM |
Access Booster |
0930-1130 |
Repair thermocouples |
Weghorn |
Access Zone B |
0930-1130 |
Pump P-RF2 alignment |
Swetin |
No Beam SRRF off |
1100-1300 |
Replace leaking flag actuator and work on LTP screens |
Diag |
Access Linac |
1330-1500 |
Recover injectors and storage ring |
OPS |
Stored beam and injection |
1500-1530 |
Check beam orbit with new offsets (I > 160 mA) |
Emery/Cheng/Dick |
Stored beam and injection |
1530-1600 |
Change LB+ to cross-bar switch (I > 160 mA) |
Cheng |
Stored beam and injection |
1500-1600 |
LFC tuning (parasitic with stored beam) |
Borland |
Stored beam and injection |
1600-1800 |
Operator training (08-18) |
Ops |
Limited injection |
1800-2000 |
Operator training (18-06) |
Ops |
Limited Injection |
2000-2400 |
FOFB in S03 |
Carwardine |
Stored beam & injection |
|
Tuesday October 7, 2025 |
|
|
0000-0600 |
RF cavity conditioning (may go till 0700) |
Ops |
Stored beam & injection |
0500-0600 |
SR final checkout |
Emery |
Stored beam & injection |
0600-0800 |
Injector training/prepare for user beam |
Ops |
Stored beam & injection |