Machine Studies

Draft Schedule for Run03-4, 2025

October 6 0800 – Ocotber 7 0800



Time

Descriptions

Studiers

SR Status


Monday, October 6, 2025



0800-0830

RF “micro conditioning with beam”

OPS

Current increase at 2 min intervals

0900-1100

Laser alignment

Dooling

Access Linac

0900-1000

BTS sigma matrix code test

C. Xu

No beam

0900-1000

Update SR bpm offsets

Emery/Cheng/Dick

No beam

0930-1030

Replace blower

MOM

Access Booster

0930-1130

Repair thermocouples

Weghorn

Access Zone B

0930-1130

Pump P-RF2 alignment

Swetin

No Beam SRRF off

1100-1300

Replace leaking flag actuator and work on LTP screens

Diag

Access Linac

1330-1500

Recover injectors and storage ring

OPS

Stored beam and injection

1500-1530

Check beam orbit with new offsets (I > 160 mA)

Emery/Cheng/Dick

Stored beam and injection

1530-1600

Change LB+ to cross-bar switch (I > 160 mA)

Cheng

Stored beam and injection

1500-1600

LFC tuning (parasitic with stored beam)

Borland

Stored beam and injection

1600-1800

Operator training (08-18)

Ops

Limited injection

1800-2000

Operator training (18-06)

Ops

Limited Injection

2000-2400

FOFB in S03

Carwardine

Stored beam & injection


Tuesday October 7, 2025



0000-0600

RF cavity conditioning (may go till 0700)

Ops

Stored beam & injection

0500-0600

SR final checkout

Emery

Stored beam & injection

0600-0800

Injector training/prepare for user beam

Ops

Stored beam & injection