Draft Schedule for Run03-5, 2025

October 13 0800 – October 15 0800



Time

Descriptions

Studiers

SR Status


Monday, October 13, 2025



0830-1030

Update firmware

Kreps

No Beam

0830-1030

M1 balancing

Rafael

No Beam

0830-1030

FOFB testing

Carwardine

No Beam

0900-1500

6ID front end repair and 16ID investigation

Clute

Access Zone A & B

1000-1200

Laser alignment

Dooling

Access Linac

1500-1700

Recover injectors and storage ring

OPS

Stored beam and injection

1600-1800

Operator training (06-18)

Ops

Limited Injection

1800-2000

Injector training (18-06)

Ops

Limited Injection

2000-0200

Assess need for S01 collimator using vertical orbit to trip MPS

Borland

Stored beam & injection


Tuesday October 14, 2025



0200-0300

Check high-intensity Robinson instability limit

Emery

Stored beam & injection

0300-0700

BTS sigma matrix

C. Xu

Limited Injection

0300-0700

FOFB

Carwadine

Limited Injection

0730-1030

Continue 6ID repairs

Clute

Access Zone A

0730-1030

Spare DCCT repair

Keane

Access Zone F

0700-1100

RG1

Sun

Access Zone F

1030-1230

Recover injectors and storage ring

OPS

Stored beam and injection

1230-1600

LFB phase sensing using borrowed 1.4 Ghz front-end in TFB

Kallakuri

Stored beam and injection

1600-1800

Operator training (06-18)

Ops

Limited Injection

1800-2000

Injector training (18-06)

Ops

Limited Injection

2000-0000

DA/LMA aperture

Borland

Stored beam & injection


Wednesday October 15, 2025



0000-0100

LFC beam motion

Borland

Stored beam & injection

0100-0400

Tune measurement of magnet hysteresis error

C. Xu

Stored beam & injection

0400-0600

Set up SR for operations

Emery

Stored beam & injection

0600-0800

Injector training/prepare for user beam

Ops

Stored beam & injection