Machine Studies
Draft Schedule for Run03-6, 2025
October 20 0800 – October 21 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, October 20, 2025 |
|
|
0830-0900 |
Reboot ioc2bacnet |
Smith |
No Beam |
0830-0930 |
Reboot sioc2injorch1 |
Fors |
No Beam |
0830-1030 |
Test chassis at K6 |
Yawei |
No Injection |
0830-0930 |
Add alarms to DAQ TBT and PS iocs |
E. Chandler |
No Beam |
0830-1030 |
Test Libera synthetic data/HCOLL |
Grass |
No Beam |
0830-1230 |
Restore DCCT meter synchronization |
Grass/ Fors |
No Beam |
0830-1430 |
Spot knock RF-4 |
RF Group |
No Beam |
0900-1000 |
PSS End to End test |
McNamara |
No Beam |
0900-1100 |
Replace leaking flag actuator |
Kisbaugh |
Access Linac |
0900-1200 |
Troubleshoot PAR RF tuner drive |
Berenc |
Limited Injection |
0930-1100 |
Replace thermocouples |
Weghorn |
Access Zone C |
1100-1230 |
Restore linac and SR magnets |
Ops |
No beam |
1230-1430 |
Test fix for missing 4th linac pulse (linac is recovered) |
Calvey |
No Beam |
1430-1600 |
Check out operational lattice for good correction. Possible other orbit measurement due to M1 and M2 droops. |
Emery |
Stored beam & injection |
1430-1600 |
FOFB parasitic tests |
Carwardine |
Stored beam & injection |
1600-1800 |
Operator training (08-18) |
Ops |
Limited injection |
1800-2000 |
Injector training (18-06) |
Ops |
Limited Injection |
2000-2300 |
DA and MA measurement |
Borland |
Stored beam & injection |
2300-0300 |
RG1 |
Y. Sun |
Stored beam & injection |
|
Tuesday October 21, 2025 |
|
|
0300-0500 |
Open |
|
Stored beam & injection |
0500-0600 |
SR final checkout |
Emery |
Stored beam & injection |
0600-0800 |
Injector training/prepare for user beam |
Ops |
Stored beam & injection |