Machine Studies

Draft Schedule for Run03-7, 2025

October 27 0800 – October 28 0800



Time

Descriptions

Studiers

SR Status


Monday, October 27, 2025



0830-0930

Swap SR DCCT DVMs

Keane

No Beam

0830-0930

Study LB+

Grass

No Beam

0830-1030

SR septum supply measurements

Abid

No Beam

0830-1030

Upgrade unipolar PS firmware

Kreps

No Beam

0830-1130

PAR RF-1 tuner PS investigations

Berenc

No Injection

0830-1130

DK and IK digitizer

Paskvan

No Beam

0830-1430

Testing of PAR amplifier/possible switch to tube amplifier

Smith, Mohsen

Limited Injection

0830-1430

Replace filter in BLS LN2 phase separator bayonet connection

Fuerst

No Beam

1430-1600

Recover SR and injectors

OPS

Stored Beam and Injection





1600-1800

Operator training (08-18)

Ops

Limited injection

1800-2000

Injector training (18-06)

Ops

Limited Injection

2000-2400

DA with various chromaticity values

Borland Emery

Stored Beam and Injection


Tuesday October 28, 2025



0000-0400

IIR filtering and its response;Effect of crossbar switch to Spark BPMs

Weixing

Stored beam & injection

0000-0400

FOFB (in parallel with Weixing)

Carwardine

Stored beam & injection

0400-0500

Open


Stored beam & injection

0500-0600

SR final checkout

Emery

Stored beam & injection

0600-0800

Injector training/prepare for user beam

Ops

Stored beam & injection