Machine Studies
Draft Schedule for Run03-8, 2025
November 3 0800 – November 5 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, November 3, 2025 |
|
|
0815-1200 |
Replace PAR-12 amplifier |
Smith |
No Injection |
0830-0930 |
ITS cable pull |
Dooling/HP/MOM |
No Injection |
0830-1030 |
Troubleshoot PAR septum |
Puttkammer |
No Injection |
0830-1030 |
Test run and measure B:IS |
Abid |
Limited Injection |
0830-1030 |
Investigate M1 imbalance |
Rafael |
No Beam |
0830-1030 |
Upgrade L3:QM3 |
Yang |
No Injection |
0830-1130 |
investigate a tuner issue at S37 |
Madden |
No Beam |
0900-1000 |
Replace RF-4 klystron blower |
Wright |
No Beam (Access not required) |
0900-1100 |
Deploy new IOCs for IES and LB+ |
Grass |
No Beam |
0900-1100 |
Replace opto-isolator chassis for PAR RF-1 |
Berenc |
No Injection |
0900-1500 |
Vibration measurements |
Preissner |
Access Zone A & B All SR pumps and PS off |
0930-1130 |
Linac cable pull |
Dooling/HP/MOM |
Access Linac |
0930-1130 |
Replace Flag Actuation Interlock Chassis |
Kishbaugh |
Access Linac |
1100-1300 |
Ramp FID at S38 & 39 |
Grass |
No Beam |
1300-1130 |
Update S39 digitizer of IK no beam |
Paskvan |
No Beam |
1200-1400 |
Set up RF12 in PAR |
Mohsen Berenc |
No Beam |
1400-2000 |
High charge set up PAR/Booster |
Mohsen Calvey |
No Beam, mostly |
1500-1700 |
SR zones, pumps, and magnet recovery |
Ops MOM |
Limited Injection |
|
|
|
|
2000-2200 |
Operator training (18-06) |
Ops |
Limited Injection |
2200-2400 |
Test DA measurement using faster ramp rate for kickers |
Borland |
Stored beam & injection |
|
Tuesday November 4, 2025 |
|
|
0000-0400 |
Testing of software for DA and lifetime optimization |
Borland, Kuklev, Emery |
Stored beam & injection |
0400-0800 |
S36 temperature scan > 73 deg F for stable setting. 200 mA, 216 bunches |
Kallakuri Emery |
Stored beam & injection |
0800-1200 |
FOFB |
Carwardine Kallakuri |
Stored beam & injection |
1200-1300 |
Check steering with x-ray bpms |
Emery Dick |
Stored beam & injection |
1300-1600 |
BLS tuning for 48 bunches |
Kelly, Fuerst |
Stored beam & injection |
1300-1600 |
IIR filtering and its response; Effect of crossbar switch to Spark BPMs
|
Cheng |
Stored beam & injection |
1600-1800 |
Operator training (06-18) |
Ops |
Limited Injection |
1800-2000 |
Operator training (18-06) |
Ops |
Limited Injection |
2000-0000 |
BTS sigma |
Xu |
Limited Injection |
|
Wednesday November 5, 2025 |
|
|
0000-0200 |
LFB setup for operations, 48 bunches |
Kallakuri |
Stored beam & injection |
0200-0500 |
RG1 |
Sun |
Stored beam & injection |
0500-0600 |
Set up SR for operations |
Emery |
Stored beam & injection |
0600-0800 |
Injector training/prepare for user beam |
Ops |
Stored beam & injection |