Draft Schedule for Run01-5, 2026

March 2 0800 – March 3 0800



Time

Descriptions

Studiers

SR Status


Monday, March 2, 2025



0800-0830

Response matrix measurement at 10 mA. Injection stops at 0830h. Stored beam present till 0900h if needed.

Emery

Stored beam & injection

0830-1130

PAR RF12 DLLRF adjustment. Need PAR beam.

Mohsen, Berenc

No Beam

0900-1100

IES DG testing /LB+ FrozenM update

Grass

No Beam

0900-1100

Investigate/swap-out SR Converter S24:AQ4 power supply

Vargas

No BeamNo Beam

0900-1230

Update PS controller iocs and add diagnostics

B. Chandler

No Beam

0900-1100

DAQ IOC work

E. Chandler

No Beam

0930-1130

Repair water leak

Moonier

Access Zone F

0930-1130

Troubleshoot repair S38B:P6

Kishbaugh

Access Zone F

1130-1230

Verify the water flow switch in the PAR Dipole power supply. Check with RF12 studiers if time is really available.

Puttkammer

No Injection

1130-1230

Run PAR Dipole and Kickers power supplies at the 450Mev energy Check with RF12 studiers if time is really available.

Rafael

No Injection

1230-1330

Investigate FOK in SR

Abid

No Beam

1230-1400

SR recovery

Ops

Stored beam & injection

1400-1600

M1/M2 power supply “glitch” measurements. Take PSDAQ and TBTDAQ data. 10 mA.

Paskvan

Stored beam & injection

1600-1800

Operator training

Ops

Stored beam & injection

1800-2000

Operator training

Ops

Stored beam & injection

2000-2200

Examine excessive IEX orbit perturbation seen last week

Emery Chenran

Stored beam & injection

2200-2400

Testing tune knobs. 10 mA.

Chenran

Stored beam & injection


Tuesday March 3, 2025



0000-0400

FOFB in S09

Carwardine

Stored beam & injection

0400-0600

SR set up

Emery

Stored beam & injection

0600-0800

Injector training/prepare for user beam

Ops

Stored beam & injection