Machine Studies
Draft Schedule for Run01-9, 2026
March 30 0800 – March 31 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, March 30, 2025 |
|
|
0800-0900 |
Response matrix measurement at 10 mA. Injection stops at 0830h. Stored beam present till 0900h if needed. |
Dick |
Stored beam & injection |
0900-1000 |
Reboot siocrunctrl2 |
Shifu |
No Beam |
0830-0930 |
LEA ioc work. No Impact on SR |
Grass |
Part Stored beam |
0900-1100 |
Replace pump HMI. Limited impact |
Wright |
No Beam |
0900-1300 |
Install a waveguide shorting plate at RF2, swap amplifier unit in S36-C1 SSA, re-orientate S37 hybrid |
RF group |
No Beam |
0930-1100 |
Test the S38 collimator viewport camera |
Dooling |
Access Zone F |
1100-1200 |
Recover BTS and SR |
OPs |
No Beam |
1200-1400 |
BTS emittance measurement. Beam in BTS only |
C. Xu Shang |
No Beam |
1200-1400 |
new PAR BDM scope |
Mohsen, Dooling |
No Beam |
1200-1400 |
SR magnet conditioning tests |
Soliday Emery |
No beam |
1400-1600 |
Some bpm offset; check of BLS feedforward GUI functions; sundry items |
Emery |
Stored beam & injection |
1600-1800 |
Operator training |
Ops |
Stored beam & injection |
1800-2000 |
Operator training |
Ops |
Stored beam & injection |
2000-2400 |
Consolidation of lifetime improvements from 24-family MOBO |
Kuklev Borland Emery |
|
|
Tuesday March 31, 2025 |
|
|
0000-0400 |
FOFB effectiveness at different MOFB_FOFB different gains and rates |
Carwardine |
Stored beam & injection |
0400-0600 |
SR set up |
Emery |
Stored beam & injection |
0600-0800 |
Injector training/prepare for user beam |
Ops |
Stored beam & injection |