Draft Schedule for Run02-3, 2026
June 8 0800 – June 9 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, June 8, 2025 |
|
|
0800 |
No response matrix measurement today |
Nobody |
No Beam |
0800-0900 |
Full conditioning of SR magnets |
Ops |
No Beam |
0800-0930 |
Ranging a PAR thyratron |
Puttkammeer |
No beam |
0800-1200 |
Adjust S36-C4 circulator bias and optimize amplitude and phase adjustments on S36-C4 |
RF Group |
No Beam |
0800-1200 |
Perform updates to the Sector 36 PLC operating program and check calibration of S36 SSA rf power readback values. |
RF Group |
No Beam |
0800-1000 |
SR FOK controls update |
Hong |
No Beam |
0930-1200 |
PAR console testing |
Lawson/Fystro |
Limited Injection |
1000-1200 |
Remote ID01 and ID06 magnetic measurement |
Li |
No Beam |
1030-1200 |
Calibrate BIS PS |
Abid |
No Beam |
1100-1200 |
Reboot siociramp |
Shifu |
No Beam |
1200-1600 |
a) Measure ac line-to-rf
efficiency of SSA with 200 mA beam |
Horan |
SR Beam and Injection |
1600-1800 |
Operator training (08-18) |
Ops |
Limited injection |
1600-1800 |
CU steering test with beam (during PAR training) |
Shang |
SR beam and Limited Injection |
1800-2200 |
FOFB |
Carwardine |
SR beam and Injection |
2200-0200 |
PAR tune measurement |
Mohsen |
SR beam and Injection |
|
Tuesday June 9, 2025 |
|
|
0200-0400 |
Find high-intensity Robinson Instability limit (somewhere below 4.8 MV of main rf voltage) |
Emery |
Stored beam & injection |
0400-0600 |
SR set up |
Dick |
Stored beam & injection |
0600-0800 |
Injector training/prepare for user beam |
Ops |
Stored beam & injection |