Machine Studies

Draft Schedule for Run02-3, 2026

June 8 0800 – June 9 0800



Time

Descriptions

Studiers

SR Status


Monday, June 8, 2025



0800

No response matrix measurement today

Nobody

No Beam

0800-0900

Full conditioning of SR magnets

Ops

No Beam

0800-0930

Ranging a PAR thyratron

Puttkammeer

No beam

0800-1200

Adjust S36-C4 circulator bias and optimize amplitude and phase adjustments on S36-C4

RF Group

No Beam

0800-1200

Perform updates to the Sector 36 PLC operating program and check calibration of S36 SSA rf power readback values.

RF Group

No Beam

0800-1000

SR FOK controls update

Hong

No Beam

0930-1200

PAR console testing

Lawson/Fystro

Limited Injection

1000-1200

Remote ID01 and ID06 magnetic measurement

Li

No Beam

1030-1200

Calibrate BIS PS

Abid

No Beam

1100-1200

Reboot siociramp

Shifu

No Beam

1200-1600

a) Measure ac line-to-rf efficiency of SSA with 200 mA beam
b) Response time of RF3 subject to a S36 SSA/cavity trip

Horan

SR Beam and Injection

1600-1800

Operator training (08-18)

Ops

Limited injection

1600-1800

CU steering test with beam (during PAR training)

Shang

SR beam and Limited Injection

1800-2200

FOFB

Carwardine

SR beam and Injection

2200-0200

PAR tune measurement

Mohsen

SR beam and Injection


Tuesday June 9, 2025



0200-0400

Find high-intensity Robinson Instability limit (somewhere below 4.8 MV of main rf voltage)

Emery

Stored beam & injection

0400-0600

SR set up

Dick

Stored beam & injection

0600-0800

Injector training/prepare for user beam

Ops

Stored beam & injection