Machine Studies
Draft Schedule for Run02-5, 2026
June 22 0800 – June 23 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, June 22, 2026 |
|
|
0800-0830 |
Response matrix measurement at 10 mA. Injection stops at 0830h. Stored beam present till 0900h if needed. |
Dick |
Stored beam & injection |
0900-1100 |
Adjust pressure on water branch supplying S36 SSA loads |
Swetin |
No Beam |
0900-1100 |
Reboot and test H-Colimator motor's alarm limit |
Grass |
No Beam |
0900-1100 |
Update DAQ TBT and DAQ PS IOC and services |
Chandler |
No Beam |
0900-1100 |
BLS studies. No beam. |
Berenc/Kelly |
No Beam |
0900-1100 |
Calibrate BIS |
Abid |
No Injection |
0900-1100 |
Investigate Par Dipole Output Current |
Puttkammer |
No Injection |
0900-1100 |
move the P2IK injection discharge trigger |
Hong |
No Injection |
1100-1300 |
PAR Harmonic RF Feedback Characterization |
Berenc |
Limited Injection |
1300-1310 |
Fill some beam in SR to decay for any purpose |
Ops |
Stored beam & injection |
1300-1700 |
Linac tune up for injector high charge |
Sun |
Stored beam & Limited injection |
1700-1800 |
Injector training (08-18). One hour only. |
Ops |
Limited injection |
1800-2100 |
Check sextupole optional cycling in magnet conditioning. No beam |
Emery |
No beam |
1800-2100 |
PAR high charge |
Mohsen |
No beam |
2100-2300 |
Continue DAQ TBT measurements yo resolve turn synchronization problem |
Sajaev Emery |
Stored beam & injection |
2300-0200 |
Gas scattering lifetime 200 mA various bunch patterns II |
Emery |
Stored beam & injection |
|
Tuesday June 23, 2026 |
|
|
0200-0400 |
Injector training (18-06) |
Ops |
Limited Injection |
0400-0600 |
SR set up |
Dick |
Stored beam & injection |
0600-0800 |
Injector training/prepare for user beam |
Ops |
Stored beam & injection |