Machine Studies
Draft Schedule for Run02-8, 2026
July 20 0800 – July 21 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, July 20, 2025 |
|
|
0800-0900 |
Response matrix measurement at 10 mA. |
|
Stored beam & injection |
0900-1000 |
Test machine mode PEM |
Shang |
No Beam |
0900-1100 |
Swap 136 Mhz DC power supply |
Yawei |
No Impact |
0900-1100 |
Investigate PAR dipole |
Vargas |
Limited Injection |
1100-1300 |
Fill SR once. SR steering testing |
Shang |
Stored beam & injection |
1100-1300 |
PAR high charge |
Mohsen |
Stored beam & injection |
1300-1700 |
BLS signals during quenches plus scans |
Emery, Berenc, Kelly |
Stored beam & injection |
1700-2100 |
FOFB feed-forward of 60 Hz |
Carwardine |
Stored beam & injection |
2100-2300 |
Operator training |
Ops |
Stored beam & injection |
2300-0400 |
SR Dipole magnet hysteresis error measurement (by tunes) |
Emery |
Stored beam & injection |
|
Tuesday July 21, 2025 |
|
|
0400-0600 |
SR and BLS set up |
Emery |
Stored beam & injection |
0600-0800 |
Injector training/prepare for user beam |
Ops |
Stored beam & injection |