Draft Schedule for Run03-5, 2026

October 5 0800 – October 6 0800



Time

Descriptions

Studiers

SR Status


Monday, October 5, 2026



0800-0900

Response matrix measurement

Dick

Stored beam & injection

0820-0900

Linac, LPL, Booster setup. SR only needs turns counter. Other RF ramping.

Yine, Osama, Joe

No Beam

0900-0930

Linac tuning 425 MeV

Yine

No Beam

0930-0945

PAR tuning 425 MeV

Mohsen

No Beam

0945-1000

Booster setup 425 MeV

Calvey

No Beam

1000-1200

PAR kicker waveform monitoring

Paskvan

Limited Injection

0900-1100

Investigate S10 PS controller noise

Kreps

No Beam

1000-1300

Booster console testing

Lawson/Fystro

Limited Injection

1300-1400

Install microphone from utility corridor and record septum acoustic data. We can only start after the above console test is finished.

Suthar

No Beam.

1315-1400

ITS work

Popovic

Access ITS

1400-1430

Recover linac

Ops

No Beam.

1430-1600

S29-FOFB studies with IEX

Carwardine

Stored beam & injection

1600-1800

Operator training

Ops

Stored beam & injection

1800-2200

Booster digital LLRF feedback with beam

Calvey Berenc Mohsen

Stored beam & injection

2200-2400

Injector training

Ops

Stored beam & injection


Tuesday October 6, 2026



0000-0200

Check of BLS operation 48 bunches decay

Emery

Stored beam & injection

0200-0400

Conditioning tests with orbit response measurements and possible optics correction

Dick Emery

Stored beam & injection

0400-0600

SR set up

Dick

Stored beam & injection

0600-0800

Injector training/prepare for user beam

Ops

Stored beam & injection