Machine Studies
Draft Schedule for Run03-6, 2026
October 12 0800 – October 14 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, October 12, 2025 |
|
|
0800-0900 |
Orbit Response |
Dick |
Stored Beam and Injection |
0830-0900 |
switch linac rf to async |
Hong (?) |
Stored Beam and No Injection |
0900-0930 |
Replace K5 chassis. K5 down. |
Yawei |
No beam |
0900-1100 |
Investigate 15ID photon shutter |
Clute |
Zone B, AA |
0900-1200 |
K4 troubleshooting. Results determines which of the blue or red highlighted studies are done |
Meyer |
No beam |
0900-1200 |
Setup for Mode-0 correction with S37-FOFB controller. No beam |
Kallakuri, Carwardine |
No beam |
0900-1200 |
PCG beam to L3 |
Y Sun |
No beam |
1200-1300 |
Restore linac timing; Energy switch to 425 MeV in all injector machines |
Y. Sun, Mohsen, Calvey |
No beam |
1200-1500 |
Energy switch to 300 MeV in all injector machines |
Y. Sun, Mohsen, Calvey |
No beam |
1300-1500 |
Test the new pvgroup/steering application |
Shang, E. Chandler |
Stored Beam and Injection |
1500-1700 |
Test the new pvgroup/steering application |
Shang, E. Chandler |
Stored Beam and Injection |
1600-1800 |
Operator training. See above status for options in start time |
Ops |
Stored Beam and Injection |
1800-2200 |
XBPM study in S04 |
W. Li |
Stored Beam and Injection |
2200-2400 |
Re-measure the BLS voltage FF table for beam decay with 48 bunches 130 mA |
Emery |
Stored Beam and No Injection |
2200-2400 |
Open |
|
|
|
Tuesday, October 13, 2025 |
|
|
0000-0200 |
Operator training |
Ops |
Stored Beam and Injection |
0200-0600 |
Open |
|
Stored Beam and Injection |
0600-0700 |
Open |
|
Stored Beam and Injection |
0700-0930 |
Linac console testing |
Basiorka/Fystro |
Limited Injection |
1000-1130 |
Laser alignment |
Dooling |
Access Linac |
1130-1500 |
RF Gun Survey & alignment |
Waldschmidt/Survey |
Access Linac |
1500-1800 |
Orbit-to-RF phase feedback algorithm for CBM0 correction. 15 mA and higher. |
Kallakuri, Carwardine |
Stored Beam and Injection |
1800-2000 |
Operator training |
Ops |
Stored Beam and Injection |
2000-2400 |
PC gun in linac |
C. Xu |
Stored Beam and No Injection |
|
Wednesday, October 14, 2025 |
|
|
0000-0400 |
PC gun in linac (cont’d) |
C. Xu |
Stored beam & No injection |
0400-0600 |
Set up SR + orbit response and chromaticity measurements |
Dick |
Stored beam & injection |
0600-0800 |
Injector training/prepare for user beam |
Ops |
Stored beam & injection |