Machine Studies /Intervention
Schedule for Run 1998-5-8

December 8th 1998, 0800 -- December 8th, 1998 1600

Time

Tuesday, December 8th, 1998

Studiers

0800-0845

RF setup for singlets

Nassiri, Harkay

0845-0900

S36C1 adjustements

Nassiri

0900-1000

Singlets scrape down

Decker

1000-1130

Effects of SCDU triggering on the injection scan method. (10-20 mA fills)

Lill

1130

Fill: 10mA in 6, maintained until 1430 for parasitic chopper studies.

Borland

1130-1200

LINAC ACIS-related tests.
No injection during this time.

Lewellen
et. al.

1130-1330

Measurement of small-gap bpm offsets with RT feedback system using 1130 fill pattern.

Carwardine

1330-1530

Bunch purity. Beam may be dumped and refilled in arbitrary pattern at 1430.

Sereno

1530-1600

Prepare beam for user operations

Ops