Time
|
Descriptions
|
Studiers
|
SRStatus
|
|
Tuesday, 11/09/1999
|
|
|
0800-0900
|
Adjust the new couplers installed for parallel operations
|
Nassiri
|
No beam
|
0800-0900
|
Finalize the RF4 orphan load solenoid valve interlock system located at RF1
|
Horan
|
No beam
|
0800-0900
|
replace S16A:V3
|
PS group
|
No beam
|
0800-1100
|
replace process water system controller for sectors 29/30
|
Swetin
|
No beam
|
1000-1100
|
study the RF4 phase loop jump problem
|
Horan
|
No beam
|
1100-1500
|
Miscellaneous bpm repairs and studies
|
Decker
Lester
Lill
Singh
|
Stored beam and injection
(parasitic)
|
1200-1400
|
Shielding verification of 4-ID-A
|
Mohan
4-ID-A User
|
Stored beam and injection
|
1100-1400
|
Steering studies
|
Emery
|
Stored beam and injection
(parasitic)
|
1400-1530
|
Kicker scan and SR injection studies
|
Emery
|
Stored beam
and injection
|
1530-1600
|
Ready for User beam
|
Ops
Yao
|
Stored beam and injection
|