Machine Studies
Draft Schedule for Run01-9, 2024
July 30th 0800 – July 31st 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, July 30, 2024 |
|
|
0800-0900 |
Test steering script |
Berkland |
Stored Beam & Injection |
0900-1100 |
Verify K5/6 interlock configuration |
Yang |
No Injection |
0900-1300 |
Injector training |
Ops |
Limited Injection |
0930-1130 |
Update firmware for zone B and E |
PS Group |
No Beam |
0930-1130 |
Restore DC configuration for 4:AQ1 and test |
PS Group |
No Beam |
1000-1200 |
Remove hard stops and perform end to end tests |
McNamara |
Access Zone A |
1000-1300 |
9ID survey (open 10BM ratchet door) |
S/A |
Access Zone B |
1000-1400 |
Initial placement of ID at S15 |
Donnelly |
Access Zone B |
1300-1700 |
Troubleshoot 1hz noise on bipolar supplies |
PS Group |
No Beam |
1700-1900 |
Recover SR beam |
AOP/Ops |
Stored Beam & Injection |
|
|
|
|
|
Wednesday, July 31, 2024 |
|
|
2400-0200 |
Injector training |
Ops |
Limited Injection |
2400-0800 |
Vacuum conditioning |
Ops |
Stored Beam & Injection |