Machine Studies
Draft Schedule for Run01-10 2025
April 1 0800 – April 2 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, April 1, 2025 |
|
|
0815-1000 |
PC Gun drive laser installation support |
Erwin |
No Injection/Access ITS |
0815-1000 |
Replace flag actuator chassis |
Kishbaugh |
No Injection/Access ITS |
0815-1000 |
Replace S39 IETS trigger chassis |
Fors |
No Injection |
0815 |
Reboot siocrunctrl2 |
Berkland |
No Injection |
0815-1000 |
Reboot/swap controller training |
Kreps |
No Beam |
|
|
|
|
1100-1400 |
Booster extraction studies |
Calvey Dooling |
Stored Beam and Injection |
1400-1500 |
adjust the injector energy/phase |
Emery |
Stored Beam and Injection |
1500-1600 |
Check Slow Beam Abort at low currents |
Emery |
Stored Beam and Injection |
1600-1800 |
SR injection efficiency study |
Shang |
Stored Beam and Injection |
1800-2200 |
All gaps closed at low current |
Borland |
Stored Beam and Injection |
2400-2400 |
Calibrate kicks from DK and IK using Spark bpms |
Borland |
Stored Beam and Injection |
|
|
|
|
|
Tuesday April 2, 2025 |
|
|
0000-0200 |
Microwave instability measurement at high per bunch current |
Cheng |
Stored Beam and Injection |
0200-0400 |
Injector training (18-06) |
Ops |
Limited Injection |
0400-0600 |
Verify 48 bunch operation |
Emery |
Stored Beam and Injection |
0600-0800 |
Recover SR systems/prepare for user beam |
Ops |
Stored Beam and Injection |