Draft Schedule for Run03-7, 2026

October 19 0800 – October 20 0800



Time

Descriptions

Studiers

SR Status


Monday, October 19, 2026



0800-0900

Response matrix measurement

Dick

Stored beam & injection

0830-1000

Linac K4 conditioning. Strive for 425 MeV linac beam after this

Meyer

Stored beam & No injection

0900-1700

RF Group SSA work

RF Group

No Beam

0900-1100

Investigate power supply P4V2

Puttkammer

No Beam

0900-1000

Pem conditioning test with no beam

C. Xu

No Beam

0930-1130

Install a coax cable from the Pearson coil

Keane

No Beam

1000

Start recovering injectors for 425 MeV if feasible in parallel with below

Y. Sun, Mohsen, Calvey

No Beam

1000-1600

ICR VID100 testing using RG2/PCG beam. Impacts the 1 Hz/60Hz signals.

Y. Sun, R. Hong et al.

No Beam

1100-1400

PCB-coil based magnet measurements for S01DSID and S11USID

Wei

No Beam

1600-1800

Operator training

Ops

Stored beam & injection

1700-1800

SR recovery (check start time with rf group)

Ops

Stored beam & injection





1800-2100

Orbit to RF phase feedback with S37-FOFB

Kallakuri Carwardine Brill

Stored beam & injection

2100-2300

Evaluate SR 1 Hz motion under various conditions

Cheng

Stored beam & injection

2300-0100

Pem conditioning software test with beam, i.e. measure tunes

C. Xu

Stored beam & injection


Tuesday October 20, 2026



0100-0300

Operator training

Ops

Stored beam & injection

0300-0400

Open


Stored beam & injection

0400-0600

SR set up

Dick

Stored beam & injection

0600-0800

Injector training/prepare for user beam

Ops

Stored beam & injection