Draft Schedule for Run01-4, 2025

February 17 0800 – February 18 0800



Time

Descriptions

Studiers

SR Status


Monday, February 17, 2025



0800-1100

Storage Ring RF2 Driver Amp Noise Investigation

Berenc

No Beam

0830-0930

ITS measurements/inpection

SI/DIAG

No Injection

0830-0930

Inspect PC gun area for drive laser

Dooling

Access Linac

0830-1030

Replace leaking flag actuator

Kisbaugh

Access Linac

0830-1430

P1K thyratron repair

Puttkammer

Access PAR

0900-1000

Change DCCT DVM1 setting))I

Grass

No Beam

0900-1000

Downgrade the Unipolar power supply firmware

Kreps

No Beam

0900-1000

Reboot MPS IOCS

Smith

No Beam

0900-1000

Update BLS security

DiMonte

No Beam

0900-1100

Troubleshoot PS-1

Clute/SI

Access Zone B

1030-1130

Replace PAR tune amplifiers

Kisbaugh

Limited Injection

1100-1230

Recover SR systems

Ops

No Injection

1100-1300

PAR Harmonic Voltage Control Loop Adjustments

RF group

No Injection

1500-1700

Linac console testing

Urban/Fystro

No Injection

1500-1700

Linac control law testing

Shang

No Injection

1700-2130

BLS quench limit at 100 mA swap-out

Berenc, Kelly

Stored beam & injection

2130-0030

running 200 mA with high main rf gap voltage, using same parameters as 2/10/2025 studies

Emery, Berenc, others

Stored beam & injection

0030-0230

Injector training (18-06)

Ops

Stored beam & Limited Injection

0030-0230

Septum LFC (fill and decay is possible)

Borland

Stored beam & Limited Injection

0230-0400

Open




Tuesday February 18, 2025



0400-0600

Response Matrix for MOBO optimization

Emery

Stored beam & injection

0600-0800

Injector training/prepare for user beam

Ops

Stored beam & injection