Machine Studies

Draft Schedule for Run02-6, 2025

July 14 0800 – July 15 0800



Time

Descriptions

Studiers

SR Status


Monday, July 14, 2025



0830-0900

Deploy DCCT ioc

Grass

No Beam

0830-0900

Reboot beam quality ioc

Smith

No Beam

0830-0900

Reboot sioc2iocinjorch1

Controls

No Beam

0830-1030

Repair water leak at S30 T1

Vargas

No Beam

0830-1030

Investigate 60Hz noise at S01AQ3

Kreps

No Beam

0830-1030

Investigate P1K thyratron sensor

Puttkammer

Limited Injection

0830-1030

Troubleshoot L5:SC2:VL

PS group

No Injection

0830-1030

Remove jumper from LACIS

Nguyen

Access ITS

0830-1030

Upgrade SR Raw PLC code

Ruan

No Beam

0830-1230

Spotknock RF-5

RF Group

No Injection

0830-1230

Contractor water work for RF2 SSA

Swetin

No Beam

0900-1000

Inspect BLS cryostat

Fuerst

Acces Zone F

0900-1000

Check labeling on SIO2 cables

Weghorn

Access Zone F

0900-1000

Work on FLIR camera

DIAG

Access Zone F

0900-1300

Fix taper on 8ID US

Wei

Access Zone A

1300-1430

Recover SR systems

Ops/FAC

Limited injection





1100-1400

PAR high charge study

Mohsen

Limited Injection

1400-1600

Operator training (08-18), including SR

Ops

Limited injection

1600-2100

Booster high charge studies

Calvey Mohsen

Limited Injection

1600-1800

Test the PSDAQ and DAQ on waveform monitoring

Paskvan

No Beam

1800-2100

Informal testing of K1-based swap-out permissive. Need power supplies. No injection.

Borland

No Beam

2100-2300

Operator training (08-18)

Ops

Limited injection

2300-0200

Repeat the LB+ crossbar switching test

Cheng

Stored beam & injection


Tuesday July 15, 2025



0200-0400

SR aperture at septum

Emery

Stored beam & injection

0400-0600

SR set up

Emery

Stored beam & injection

0600-0800

Injector training/prepare for user beam

Ops

Stored beam & injection