Machine Studies
Draft Schedule for Run03-14, 2025
December 22 0000 – December 23 0000
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, December 22, 2025 |
|
|
0000-0400 |
S03 FOFB. 10 mA in high charge bunch to allow PAR parasitic study |
Carwardine |
Stored beam & injection |
0000-0200 |
High charge BDM measurement in the PAR (high charge only) |
Mohsen |
Stored beam & injection |
0400-0600 |
Operator PAR training |
Ops |
Stored beam & injection |
0600 or 0700 |
Correct the cabling of MPS chassis |
Hong |
Stored beam & injection |
0600-0700 |
Check LFB functioning at high gain. Decide on LFB state for next study. |
Emery, Cheng |
Stored beam & injection |
0700-0800 |
Prepare beam 48 bunches, 130 mA |
Emery |
Stored beam & injection |
0800-0900 |
Open shutters. Beamlines prepare to measure beam motion. Steer 7BM for calibration (Cheng). |
Ops |
Stored beam & injection |
0800-0900 |
Steer 7BM for calibration |
Cheng |
Stored beam & injection |
0900-1400 |
Turn off air handling units one at a time, |
MOM, Emery |
Stored beam & injection |
0900-1400 |
Measure sector 7 x-ray bpm spectrum (parallel to above) |
Cheng |
Stored beam & injection |
1500 |
Close shutters, remove stored beam |
Ops |
Stored beam & injection |
1500-1800 |
BTS measurements |
C. Xu |
Stored beam & injection |
1800-2400 |
Optimization of lifetime and efficiency in operations lattice |
Borland, Kuklev, Emery |
Stored beam & injection |