Machine Studies
Draft Schedule for Run01-12, 2026
April 22 0800 – April 22 2400
Time |
Descriptions |
Studiers |
SR Status |
|
Wednesday, April 22, 2025 |
|
|
0800-0900 |
FOFB preparation. Shutters closed |
Carwardine, floor coordinators |
Stored Beam and Injection |
0900-1100 |
Open shutters with FOFB running |
Carwardine and some beamlines |
Stored Beam and Injection |
1100-1200 |
More FOFB characterization |
Kallakuri |
Stored Beam and Injection |
1200-1300 |
RF SR pem testing for SSA cavity |
Berkland, fystro, Soliday |
No beam |
1200-1300 |
Start a new IOC to monitor traffic (parasitic) |
Smith |
No beam |
1200-1400 |
Beam sigma measurement on LTP. Allow injection of SR at 1300h |
Chenran |
Stored Beam and Limited Injection |
1300-1400 |
Orbit response measurement 10 mA |
Dick |
Stored Beam and Limited Injection |
1400-1600 |
Booster orbit effect on rad monitors |
Calvey |
Stored Beam and Injection |
1600 |
Inject 200 mA, 216 bunches for decay |
Emery |
Stored Beam and Limited Injection |
1600-2200 |
PAR Harmonic Voltage Modulation Studies |
Mohsen, Calvey, Berenc |
Stored Beam and Limited Injection |
2200-2400 |
S40 cavity temperature scan 200 mA, 216 bunches |
Kallakuri Emery |
Stored Beam and Injection |
|
|
|
|